ARCHER, Chief Justice.
This is a bailment case. The plaintiff leased certain road building equipment to defendant. Damages were sought for allegedly holding over and for minor repairs. The trial court granted judgment for plaintiff for both holding over and for the repairs.
On July 30, 1952, defendant signed a contract and paid $3,600 for the use of some of plaintiff's equipment for a month. Although providing for use of the equipment for a month in Midland...