BRAY, P.J.
Defendants and cross-complainants appeal from a judgment in favor of plaintiff and cross-defendant in the principal sum of $5,217.60 and for foreclosure of a mechanic's lien, presenting solely the question of whether there is substantial evidence to support the finding that plaintiff's late performance was excused for 49 days.
RECORD
Plaintiff and defendants entered into a contract on October 31, 1955, in which plaintiff agreed to construct...