STONE, J. pro tem.
The defendants were awarded a contract to construct a section of state highway known as the Colton Freeway Project. Subsequently, they entered into a subcontract dated November 21, 1955, with the plaintiff who agreed to haul approximately 220,000 tons of dirt from the Portland Cement pit to the roadbed of the freeway between certain designated stations. The contract rate to be paid plaintiff was 7 1/2 cents per ton...