HILL, J.
The issue presented is whether a claim of lien was timely filed.
A contracted with C, the general contractor, to do the tile work on a residence which C was erecting for T.
C received substantial progress payments from T, including payment for the tile work, but made no payments to A.
A stopped work on August 20, 1956, at which time the