FRUGE, Judge ad hoc.
Defendant-appellant appeals from a judgment casting him in the sum of $269.22 in connection with his contract with subcontractor A. Switzer, plaintiff-appellee, herein.
This is a suit, in which the only issue is the interpretation of the provision of the plans and specifications. And that is whether certain electrical work was called for in the plans and specifications.
L. S. U., as owner, entered into a contract with defendant...