MONTGOMERY, Judge.
This action was brought by Charles E. Story, as a subcontractor, against Talbot-Tobin Contracting Company to recover the balance due under a contract. Story received judgment in the sum of $7,747.52.
Talbot-Tobin Contracting Company was the prime contractor with the Commonwealth of Kentucky, Department of Highways, for the construction of a highway between Gilbertsville and Reidland. Appellant entered into a written contract with Story,...