Matter of the Application of BIG LOST RIVER IRRIGATION DISTRICT for Approval of Plans, Drawings, and Specifications amending Plans, Drawings, and Specifications heretofore approved for Raising of Reservoir Level Five Feet at the Mackay Dam. BIG LOST RIVER IRRIGATION DISTRICT, Plaintiff-Respondent, v. Mark R. KULP, State Reclamation Engineer of the State of Idaho, Defendant-Appellant.

Supreme Court of Idaho.

February 26, 1957.


Attorney(s) appearing for the Case

Graydon W. Smith, Atty. Gen., John R. Smead, Asst. Atty. Gen., for appellant.

Robert M. Kerr, Jr., Blackfoot, for respondent.


PORTER, Justice.

In the year 1952 the Big Lost River Irrigation District filed an application with the State Reclamation Engineer for approval of plans, drawings and specifications for raising the reservoir level at Mackay Dam in Custer County an additional height of fifteen feet. The State Reclamation Engineer approved the raising of the reservoir level an additional five feet in height. The spillway of the Mackay Dam is some seventy-five feet in width. The approved...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases