MUSSELL, J.
This is an action in which plaintiff secured a judgment for $7,822.02 and costs and a decree of foreclosure of a mechanic's lien for work and labor done and performed and for materials furnished in the construction of an office building in San Diego. On June 25, 1954, plaintiff submitted a bid to the defendants (owner-builders) to furnish all labor and materials for the installation of suspended ceilings and acoustic tile work on the first and