BEARDEN v. SMITH

No. 36285.

274 P.2d 1015 (1954)

Frank BEARDEN, d/b/a Bearden Plumbing & Heating Company, Plaintiff in Error, v. Darwin C. SMITH and L. E. Smith, a co-partnership, d/b/a L. E. Smith Construction Company, Defendants in Error.

Supreme Court of Oklahoma.

Rehearing Denied October 12, 1954.


Attorney(s) appearing for the Case

Hickman & Hickman, Frank Hickman, Frank R. Hickman, Tulsa, for plaintiff in error.

Covington & Donovan, A.M. Covington, Tulsa, for defendant in error.


DAVISON, Justice.

This is an action whereby Frank J. Beardon, doing business as Beardon Plumbing and Heating Company, as plaintiff, seeks to recover from the defendants, Darwin C. Smith and L.E. Smith a partnership, doing business as L.E. Smith Construction Company, an alleged unpaid balance due on a contract for installation of plumbing, heating and air conditioning systems in a municipal hospital. The parties will be referred to as they appeared in the trial court...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases