THOMAS, Justice.
Appellant, a well drilling contractor, entered into a written contract with respondent, dated May 31, 1949, to drill a well on a designated site; the well was intended to supply water for a potato starch processing plant of respondent. At the time the contract was executed respondent made an advance of $1000 to appellant and it was agreed that respondent would pay appellant $12 per foot on the completion of the well, in accordance with the terms of...