Judgment modified on the law by striking out the award of interest and as modified affirmed, without costs of this appeal to either party.
Memorandum:
Appellant's claim rests upon an alleged breach of contract in that the general construction work did not progress concurrently with appellant's work. The alleged breach was of the following contract provision: "Related Work — The following work will be done under other contracts which will be progressed...