MR. JUSTICE CARDOZO delivered the opinion of the Court.
The power of an appellate court to modify a decree in equity for the benefit of an appellee in the absence of a cross-appeal is here to be admeasured.
Morley Construction Company, a petitioner in this court, made a contract with the United States, acting by the Veteran's Administration Department, for the construction of a veterans' hospital at Batavia, New York. In conformity with statute (40 U.S.C. § 270) it gave a bond for the completion of the contract and for the payment of all bills for material and labor, the respondent Maryland Casualty Company signing the bond as surety. During the progress of the work, the contractor found itself in need of a loan of money to enable it to go on. Accordingly a supplementary agreement was made between the contractor and the surety to relieve the situation. By that agreement, dated April 28, 1933, the contractor agreed to deposit in a designated trust company in Buffalo $5,000 to be used in the performance of the work and to deposit in the same account for the same purpose all moneys received from the United States as payments upon the contract. The surety agreed to deposit in the same account $5,000 as a loan to be secured by the contractor's note, and additional moneys sufficient to pay the present and future bills of plasterers, amounting, as the evidence shows, to $5,700. The contractor and the surety were to have joint control
Following this supplementary agreement, the contractor went on with the work, and brought it to completion. The surety made the first payment of $5,000 in accordance with its promise but refused to pay the $5,700 owing to the plasterers. In the meantime a series of payments became owing from the Government upon estimates of value in advance of completion and acceptance. Warrants for these payments were forwarded by the Government to the trust company in Buffalo to be placed in the joint account, notice having been given by the contractor to issue them accordingly. However, a different course was followed when the final payment became due. Apparently through inadvertence, the Government sent a warrant for that payment ($59,780.82) to the contractor itself at its office in Kansas City, Missouri. The contractor endorsed the warrant, delivered it to the Merchants Bank of Kansas City one of the petitioners in this court, and directed the bank to issue a cashier's check for a like amount to the order of the contractor's president. The bank made out the check, but held it to await the payment of the warrant, which it deposited in a Federal Reserve Bank to be forwarded, in the usual course of collection, to the Treasury at Washington. Neither check nor warrant has been paid as a consequence of an injunction obtained by the respondent.
Upon learning from the Veterans' Administration Department of the transmission of the warrant, the surety began two suits, one in the District of Columbia, where the payment of the warrant was stayed by an injunction, the other the suit at bar. It recounts in its complaint the facts or most of them already stated in this opinion,
The District Judge held that the surety was not entitled to the specific performance of the agreement, having failed to pay the plasterers and being therefore in default itself. He held, however, that apart from any agreement the contractor was subject to a duty to exonerate the surety from present liabilities. True, there was no purpose on the part of the contractor to divert the proceeds of the warrant from the uses of the contract. As to this the finding is explicit. Even so, a cause of action for exoneration does not include among its elements the presence of a wrongful purpose. Glades County v. Detroit Fidelity Co., 57 F.2d 449; West Huntsville Cotton Mills v. Alter, 164 Ala. 305; 51 So. 338; Pavarini v. Title Guaranty & Surety Co., 36 App. D.C. 348; Hutchinson Grocer Co. v. Brand, 79 Kan. 340; 99 Pac. 592. The decree conforms to the findings in its distribution of relief. It adjudges the complainant to be entitled to exoneration but not to specific performance.
From that decree the contractor appealed to the Circuit Court of Appeals for the eighth circuit. There was no cross-appeal by the surety. The Court of Appeals states in its opinion, "We are in grave doubt whether exoneration can properly be granted." Preferring by reason of that doubt to put its decision on some other ground, it concludes that there should be specific performance of the supplementary agreement. It concedes that the surety is in default for failing to live up to the agreement strictly, but it finds that the default was not unconscionable or fraudulent, and that a court of equity in its discretion may overlook an unsubstantial wrong. Recognizing the necessity of modifying the decree if exoneration is to be exchanged for specific performance, the opinion states that "an injunction against using the moneys except as agreed upon, and an order to place said moneys when received in the joint account and disburse the same in payment of just claims for labor or materials, would meet the requirements and rights of plaintiff and would not be impossible of performance" and that "a decree along such lines should be granted by the trial court." 84 F.2d 522, 526. Accordingly, the mandate of the appellate court provides that the cause be remanded to the District Court with directions to modify its decree in accordance with the views expressed in the opinion. We granted certiorari to fix the measure of relief available to a non-appealing suitor.
The substitution of specific performance for exoneration at the instance of the surety was not an affirmance
The surety laid claim to relief upon the basis of a contract, and to other relief by force of an equitable doctrine independent of contract. The decree of the District Court rejected the first claim because the contract had been broken, and accepted the second because the breach was then relevant. The decree was responsive to the claim that had been accepted, and not to any other. If there was to be specific performance of the contract, the surety, together with the contractor, would control the distribution of the fund, for so the parties had agreed. If there was to be exoneration and nothing more, the contractor or perhaps the court would control the application and the surety would stand aside. Stulz-Sickles Co. v. Fredburn Construction Corp., 114 N.J. Eq. 475, 478; 169 Atl. 27; cf. Glades County v. Detroit Fidelity Co., supra; Arant, Suretyship, pp. 318, 319 and cases cited. Exoneration "does not entitle the surety to custody or control of the fund." Stulz-Sickles Co. v. Fredburn Construction Corp., supra. The decision of the Court of Appeals puts an end to this nice adjustment of the relief to the law and of the law to the facts as found. A decree appropriate to exoneration is annulled, and one appropriate to specific performance is given in its place. This is to find the facts anew and differently, for the trial judge
The decree should be reversed and the cause remanded to the Court of Appeals to pass upon the question, not yet definitively answered, whether relief in the form of a decree for exoneration is proper in the circumstances, and for other proceedings in accord with this opinion.
Reversed.
Comment
User Comments