Plaintiff-subcontractor made a prima facie showing of entitlement to judgment as a matter of law by submitting a Certificate of Substantial Completion, a Final Inspection Report, and the affidavit of its secretary stating that the claimed amounts were owed and that all remaining work had been completed in accordance with the terms and conditions of the parties' contracts.
In response, defendant-general contractor failed to raise a triable issue of fact (see Alvarez...