NOT FOR PUBLICATION
MEMORANDUM*
The Summit Lake Paiute Tribe (the Tribe) filed a Petition for Review challenging the Bureau of Land Management's (BLM) decision to amend the rights of way and temporary use permits granted to Ruby Pipeline, L.L.C. ("Ruby"). That decision re-routed a four-mile segment of the pipeline, shifting it roughly one half mile north of its original route.
1. Mootness:
Ruby and BLM argue that, because the construction of the pipeline is now complete, the Tribe's National Historic Preservation Act and National Environmental Policy Act challenges are moot. In determining mootness, "the question is not whether the precise relief sought . . . is still available. The question is whether there can be any effective relief." Nw. Envtl. Def. Ctr. v. Gordon, 849 F.2d 1241, 1244-45 (9th Cir. 1988) (quoting Garcia v. Lawn, 805 F.2d 1400, 1403 (9th Cir. 1986)); see also Neighbors of Cuddy Mountain v. Alexander, 303 F.3d 1059, 1065 (9th Cir. 2002).
The majority of the harm the Tribe sought to avoid in this case stemmed from the construction of the pipeline. At oral argument, Petitioners stated that they are not seeking to have the pipeline moved, as digging it up and burying it again would only cause more damage. Nevertheless, effective relief is still available as long as the ongoing effects the pipeline continues to have on the Tribe's cultural property, such as the effects of maintaining the pipeline's right of way or lingering effects from construction, can be mitigated. We conclude that the Tribe's claims are not moot to the extent that further mitigation could provide relief, while those claims that depend on re-routing the pipeline are moot. Below, we review mootness under this standard for each claim raised.
2. National Historic Preservation Act (NHPA):
3. National Environmental Policy Act (NEPA):
We have approved of the use of such "determination" documents as the BLM prepared here, see Price Rd. Neighborhood Ass'n v. United States Dep't of Transp., 113 F.3d 1505, 1510 (9th Cir. 1997), while noting that they are not to replace supplemental environmental assessments or impact statements and may only be used "for the purpose of determining whether new information or changed circumstances require the preparation of a supplemental EA or EIS." Idaho Sporting Congress Inc. v. Alexander, 222 F.3d 562, 566 (9th Cir. 2000). When an agency takes the requisite "hard look" and "determines that the new impacts will not be significant (or not significantly different from those already considered), then the agency is in full compliance with NEPA." North Idaho Community Action Network v. U.S. Dept. of Transp., 545 F.3d 1147, 1154-55 (9th Cir. 2008). Such determinations will only be set aside if they are arbitrary and capricious. Id. at 1155.
The Tribe contends that BLM's TCP boundaries, established after the final environmental impact statement was completed, are wrong, and that the pipeline, even as re-routed, still passes through the TCP. The legal adequacy of BLM's determination that it need not supplement the environmental impact statement turns on its contrary factual conclusion regarding the size of the TCP, resulting in its repeated assertion that the re-routed pipeline "avoids direct impacts to the Summit Lake TCP." If this latter statement is accurate, it was reasonable to conclude that the circumstances after the proposed re-routing would not be significantly different from those when the environmental impact statement was drafted, as no TCP would be impacted after the re-route. In other words, the existence of the TCP was certainly significant new information, but if the pipeline avoided it entirely, then its effects would not be significantly different from those discussed in the environmental impact statement, and no supplementation would be required. In this case, determining the size of the TCP, and the determination that the re-routed pipeline passed outside it, was the type of threshold factual inquiry that may be made in a "determination" document.
The BLM's factual conclusion regarding the boundaries of the TCP was not arbitrary and capricious. BLM and the Tribe worked together to sketch out the boundaries of the TCP. When the Tribe suggested that the TCP was larger than that acknowledged by BLM, BLM conducted a series of site visits in which the Tribe had an opportunity to bring to BLM's attention sites that would suggest a larger TCP. None were found. While the Tribe blames BLM for its failure to locate any sites indicating a larger TCP during these site visits, BLM's reliance on the visits and on the pedestrian survey of the re-route conducted by Ruby's cultural resources subcontractor was not arbitrary and capricious. The record also shows that BLM considered the Tribe's main evidence for a larger TCP, the Bengston report, and determined that its own site visits and surveys were more reliable.
In short, BLM's conclusion regarding the size of the TCP was reasoned and thorough; while it may have been arguable, it was not arbitrary and capricious. Taking this conclusion as accurate, it was reasonable to conclude that the impacts of the re-route would not be "significantly different from those already considered" in the environmental impact statement. North Idaho, 545 F.3d at 1155. We therefore conclude that BLM did not act arbitrarily and capriciously in determining that no supplement to the environmental impact statement was necessary.
The petition for review is
Comment
User Comments