STAHL, Senior Circuit Judge.
This diversity case arises out of a common situation in commercial dealings: the failure of negotiations and the resulting bad blood between the parties. Here, after a protracted — and ultimately failed — nine-month negotiation between a general contractor and a potential subcontractor, the general contractor brought suit against the subcontractor for breach of contract, claiming that at some point during the negotiations a binding contract had been formed. After cross-motions for summary judgment on the question of contract formation, the district court ruled in favor of the general contractor. Because we hold that no contract was formed, we reverse.
I. Background
TLT Construction Corp. ("TLT"), a Massachusetts company, was the general contractor on renovation and expansion projects for Reading Memorial High School in Reading, Massachusetts (the "Reading Project"), and Wachusett Regional High School in Holden, Massachusetts (the "Wachusett Project"). In April 2004, as TLT was preparing its bid for the Reading Project, RI Inc., d/b/a Seating Solutions ("Seating"), a New York company specializing in selling and installing spectator seating for athletic facilities, submitted a bid to TLT to install bleachers for the Reading Project as a subcontractor. In its proposal, Seating stated, "We have worked very closely with this architect and have helped them design this bleacher from the very first steps." On the record before us, it does not appear that Seating's bid was a filed sub-bid, nor does TLT makes such a claim. See Mass. Gen. Laws ch. 149, § 44F.
On May 10, 2004, TLT, having been awarded both the Reading and the Wachusett Projects, requested that Seating submit a new quote that would include both projects. On May 12, Seating quoted a price of nearly $568,000 for both. TLT responded that the price was too high, and Seating replied on May 17 with a revised quote of $480,000. Seating said that the price was "contingent on a letter of intent being received [May 18] and an AIA contract being executed by Friday." TLT responded that day, seeking clarification of a few terms, including whether or not bonding was included in the quote, since a bond was required and had been included in the quotes from Seating's competitors. Seating responded later that day that bonding was not included in the quote, and that it did not feel bonding was necessary, since it would be paid in progress payments. TLT
Rather, four days later, on May 21, 2004, TLT sent Seating a draft contract,
The record becomes more opaque at this point. It appears that a revised draft contract may have been sent on June 7, but that draft does not appear in the record.
On June 22, Seating wrote to TLT to say that it had several issues with the draft contract. First, Seating said that it had understood that no bonding would be required, and that there would be a 10% retainage in lieu of bonding. Second, Seating wanted to clarify the timing for submission of shop drawings. Third, Seating said that its quote was made using prevailing wages, not union labor, and if TLT were to require union labor (as the May 21 draft contract did), then there would be a price increase. Fourth, Seating noted that the quote was exclusive of taxes, permits, and fees. This letter was apparently returned to Seating with notations by TLT, but that response is not in the record.
On June 28, Seating wrote to TLT, responding to TLT's notations to Seating's June 22 letter, saying that after "only a few comments" it could "get this thing executed." First, Seating said that its insurance company would not make a certain change to the language on the certificates that TLT had presumably requested. Second, it said that an umbrella policy was cost-prohibitive. Third, it requested a six-week time frame for return of engineered shop drawings. On June 29, TLT accepted the first two changes, but did not reply to the third. TLT also requested that Seating mark up the original contract with these changes and return it to TLT.
On July 5, Seating returned a marked-up version of the May 21 draft contract. The changes covered five areas. First, Seating struck all language related to payment and performance bonds and struck out the bonding forms that had been attached. Second, Seating struck the language requiring union labor. Third, Seating struck the language requiring that insurance coverage be "in the same Limits as required by the Owner's contract of the general contractor," and
The next writing in the record, perhaps after some verbal communication between the parties, is a July 12 letter from Seating to TLT. The letter provided a break-down of additional cost if union labor was to be required. Then the letter continued:
The letter closed, "If all is acceptable please forward new contracts for us to execute."
On July 21, TLT sent a new draft contract to Seating.
On July 29, TLT wrote to Seating to request the return of the signed contracts. On August 13, Seating wrote to say that its price would have to increase by $19,236 to account for an I-beam that it had not realized was in the plans.
On August 18, Seating provided a certification of insurance from Outdoor Aluminum, an affiliated company that ran Seating's factory, asking if it was "acceptable." In addition, the letter said, "Per our conversation, bonding will not be an issue. They [Outdoor Aluminum] bond many projects [for] us and unless there is something out of the ordinary all will be done."
On August 19, TLT wrote back to challenge the price increase, saying that Seating had the specifications showing the I-beam when it made the bid. At that point, relations deteriorated. Over the next few months, the parties continued to try to reach agreement, but with decreasing levels of cooperation. TLT ultimately had the work performed by another company, at a cost of $514,160.
In December 2004, TLT brought suit in Massachusetts state court for breach of contract and violation of the Massachusetts consumer protection law, Mass. Gen. Laws ch. 93A, § 11. Seating removed the case to the United State District Court for the District of Massachusetts on February 3, 2005. The parties agreed to have the case tried by a magistrate judge. The parties then cross-moved for summary judgment on the issue of contract formation. The district court held that a contract existed and that Seating had breached.
II. Discussion
We review the district court's grant of summary judgment de novo, with all reasonable inferences resolved in favor of Seating. See Fenton v. John Hancock Mut. Life Ins. Co., 400 F.3d 83, 87 (1st Cir.2005). Although the question of contract formation is typically a question for the factfinder, and would thus be subject to clear error review, see Crellin Tech., Inc. v. Equipmentlease Corp., 18 F.3d 1, 7 (1st Cir.1994), where "the evidentiary foundation for determining the formation of the parties' contract [is] either undisputed or consist[s] of writings," contract formation is instead a question of law for the court, Lambert v. Kysar, 983 F.2d 1110, 1114 n. 4 (1st Cir.1993); see Mass. Eye & Ear Infirmary v. QLT Phototherapeutics, Inc., 412 F.3d 215, 229 (1st Cir.2005); Jewelers Mut. Ins. Co. v. N. Barquet, Inc., 410 F.3d 2, 9-10 (1st Cir.2005). Here, both parties moved for summary judgment on the basis of undisputed facts.
Under Massachusetts law of contract, it is well established that "the fact that parties contemplate the execution of a final written agreement effects a strong inference that the parties do not intend to be bound by earlier negotiations or agreements until the final terms are settled." Rosenfield v. U.S. Trust Co., 290 Mass. 210, 195 N.E. 323, 325 (1935); see McCarthy v. Tobin, 429 Mass. 84, 706 N.E.2d 629, 632 (1999). "If, however, the parties orally agree to the essential terms of the transaction, it may be inferred that they intended to bind themselves at that time and that the `writing to be drafted and delivered is a mere memorial of the contract, which is already final by the earlier mutual assent of the parties to those terms.'" Novel Iron Works, Inc. v. Wexler Constr. Co., 26 Mass.App.Ct. 401, 528 N.E.2d 142, 146 (1988) (quoting Rosenfield, 195 N.E. at 325); see McCarthy, 706 N.E.2d at 632. "It is not required that all terms of the agreement be precisely specified, and the presence of undefined or unspecified terms will not necessarily preclude the formation of a binding contract." Situation Mgmt. Sys., Inc. v. Malouf, Inc., 430 Mass. 875, 724 N.E.2d 699, 703 (2000). "The parties must, however, have progressed beyond the stage of `imperfect negotiation.'" Id. (quoting Lafayette Place Assocs. v. Boston Redev. Auth., 427 Mass. 509, 694 N.E.2d 820, 826 (1998)); see Rosenfield, 195 N.E. at 326.
In a case such as this, with faxes, phone discussions, and multiple draft contracts
First, at no point did either party behave as if it had a contract. Indeed, negotiations continued for nearly six months after the date TLT claims a contract was formed. TLT does not appear to have taken any action in reliance on a contract having been formed. See Novel Iron Works, 528 N.E.2d at 146-47 (party successfully asserting contract formation was told it was the general contractor, came up with drawings and specifications, solicited bids from subcontractors, was authorized to purchase materials, obtained a building permit, etc.). TLT appears to have first approached litigation from a theory of a general contractor's reliance on a subcontractor's bid. See Loranger Constr. Co. v. E.F. Hauserman Co., 376 Mass. 757, 384 N.E.2d 176, 179 (1978). It ultimately pursued the contract theory after it became clear that Loranger did not apply.
Second, the record shows that obtaining signed contracts was important to TLT. TLT repeatedly pressed Seating for executed contracts, stating that it would not proceed with the project without them. This suggests that the parties did not intend to be bound before executing a final written agreement. See Rosenfield, 195 N.E. at 325; see also Salem Laundry Co. v. N.E. Teamsters & Trucking Indus. Pension Fund, 829 F.2d 278, 280 (1st Cir.1987) ("Parties can agree on every term in a contract, yet not be bound until they sign a written agreement, if they so indicate."); Bates v. Southgate, 308 Mass. 170, 31 N.E.2d 551, 553 (1941) ("Even though previous oral conversations would be enough in themselves to establish an oral contract the parties may, nevertheless, by mutual understanding postpone the culmination of their negotiations into a contract to the later preparation and delivery of a written instrument."); Tull v. Mister Donut Dev. Corp., 7 Mass.App.Ct. 626, 389 N.E.2d 447, 451 (1979) ("Businessmen would be undesirably inhibited in their dealings if expressions of intent and the exchange of drafts were taken as legally binding agreements.").
Neither of these points necessarily precludes a holding that a contract had formed. But neither will a failed negotiation, even one that causes damage to one or both parties, be necessarily a breach of contract.
Both parties acknowledge that the negotiations were drawn out and involved a series of offers and counteroffers. Seating argues that this is all it was, and that no offer was ever accepted, because each response was only a counteroffer. The May 21 draft contract was an offer, and Seating's return of it on July 5 with excisions was a counteroffer. This was followed by the July 21 draft contract from TLT, which, since it embodied different terms from the edited July 5 draft, was yet another counteroffer.
TLT argues that the July 5 edited draft that Seating returned actually embodied terms already agreed to in faxes and discussions, and the draft was thus an acceptance of TLT's offer. But we do not see from the record how this could be, since there is no record evidence that any of the five issues raised by the July 5 edits had previously been agreed upon. Seating
On the issue of bonding, TLT itself argues (contrary to its assertion that the July 5 agreement is binding), that the bonding issue was not agreed upon until July 12. In a letter sent by fax on that day, Seating, according to TLT, dropped its insistence on having progress payments with 10% retainage in lieu of bonding, and instead agreed to bond the project.
It is a reasonable inference — and we take all reasonable inferences in favor of Seating — that this was still just a step in the negotiation, rather than a final acquiescence. Seating notes that it understood that "it was agreed that 10% retainage would be held in [lieu] of bonding," thus acknowledging a continuing dispute on the issue. Furthermore, the letter also states that "[w]hen bonding is required we reserve the right . . . to have our factory supply the required bonds." With this last sentence Seating seems to acknowledge that bonding may or may not be required. The letter also brings up, for the first time in the record, a request that the bonding be done through Seating's factory. Given the importance of bonding in the construction industry, such a request could be a material change in terms, making the July 12 letter just another counteroffer. There is no evidence of this issue being discussed further between the parties until August 18.
TLT claims that "it is [the July 5] contract[ ] which TLT seeks to enforce. All of the Parties' subsequent communications merely entailed hammering out minor details." While "[a] written contract, signed by only one party, may be binding and enforceable even without the other party's signature if the other party manifests acceptance," Haufler v. Zotos, 446 Mass. 489, 845 N.E.2d 322, 331 (2006), we see no manifestation of acceptance here. The only communication in the record from TLT following the receipt of the July 5 draft contract is the July 21 draft contract, which on its face does not accept all of the terms of the July 5 draft contract. In addition, there is no evidence in the record that TLT took any actions that could be construed as manifesting acceptance. Furthermore, TLT's position that the July 5 draft contract should be binding is contrary to TLT's assertion that the inclusion of the bonding language in the
The only issue that appears to have actually been resolved during this period was the issue of union labor. Seating said that its bid was calculated using non-union wages, and that a union requirement would raise the price of the project. TLT removed the union labor requirement from the July 21 draft contract — the only one of Seating's five requested changes that TLT made. But because there is nothing in the record showing an agreement on this issue prior to July 5, it is a reasonable inference that the July 5 excision of union terms was an offer, with the July 21 draft being TLT's acceptance (of that term alone).
Thus, summary judgment in favor of TLT should not have been granted. Furthermore, even taking all reasonable inferences in favor of TLT, we hold that no contract was formed.
Our decision today is in part a result of the complexity of the negotiations, which is reflected in some inconsistencies in the district court's opinion. For example, the district court said at various points that: there was "an agreement in principle" on May 17, 2004; that the parties were beyond "imperfect negotiation" and that "[t]he essential terms of the agreement had been reached" as of July 5; and that the parties agreed to bonding terms on July 12. These three findings show the confusion of the process and in a sense are contradictory. Because the district court does not pinpoint with precision the point at which the contract was formed, we are inclined to view with some skepticism its conclusion.
Furthermore, the district court found that the insurance issue had been agreed to prior to July 5. But the evidence for this, a June 28 letter, does not deal with insurance limits at all. The parties only discuss the language in the certificates and the necessity of umbrella insurance. Finally, the district court explains the non-inclusion in the July 21 draft of Seating's requested language on permits and fees, insurance limits, and timing of shop drawings
III. Conclusion
For the foregoing reasons, we reverse the summary judgment order of the district court and remand with instructions that summary judgment be entered in favor of Seating.
Comment
User Comments