Ordered that the order is affirmed insofar as appealed from, with costs.
The Supreme Court properly granted that branch of the cross motion of the third-party defendant Prince Electric (hereinafter Prince) which was for summary judgment dismissing the third-party cause of action for contractual indemnification insofar as asserted against it by the defendant third-party plaintiff, JKT Construction, doing business as Corcon Construction (hereinafter JKT). In support...