The motion court correctly dismissed plaintiff's causes of action for breach of contract on the ground that the parties' 1998 letter agreement, which purported to settle plaintiff's claims for extra work performed pursuant to the parties' 1993 contract, is not separately enforceable in a court action, but rather is subject to the alternate dispute resolution procedures contained in the 1993 contract. Insofar as pertinent, the letter agreement, after resolving the extra time...