WILLIAM TOWNE ASSOCIATES, INC. v. PEGASUS CONSTRUCTION, INC.


286 A.D.2d 246 (2001)

728 N.Y.S.2d 372

WILLIAM TOWNE ASSOCIATES, INC., Appellant, v. PEGASUS CONSTRUCTION, INC., et al., Respondents.

Appellate Division of the Supreme Court of the State of New York, First Department.

Decided August 9, 2001.


Defendants' three-day-late proffer of the second of the three payments due pursuant to the parties' stipulation of settlement, after timely making the first payment, would not have justified a finding that defendants were in default under the stipulation. Neither the stipulation nor the parties' conduct demonstrates that time was of the essence (see, Ciani v Georgalas, 274 A.D.2d 443

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases