Ordered that the order is affirmed, with costs.
On October 3, 1985, the defendant the Village of Highland Falls awarded a contract to the plaintiff Morano Construction Corp. (hereinafter Morano) in the amount of $1,345,350, for the construction of a 7,000 foot interceptor sewer connecting an existing sewage treatment plant to a new plant which was under construction by a different contractor. Thereafter, Morano requested that the Village provide a change order because...