Petitioner's contention that it was the lowest bidder rests on the proposition that the bid of the winner was not responsive because of that bidder's failure to attend the "pre-bid meeting". However, the record shows that the requirement was waived. Petitioner urges that the attendance waiver was an arbitrary violation of Procurement Policy Board (PPB) Rules (9 RCNY) § 5-01 (c) which provides for automatic rejection of nonconforming bids. However, the Department had...