MATTER OF PKS DEV. CO. v. KAHN LUMBER & MILLWORK CO., INC.


187 A.D.2d 656 (1992)

In the Matter of PKS Development Company, Respondent, v. Kahn Lumber & Millwork Co., Inc., Appellant, et al., Respondents

Appellate Division of the Supreme Court of the State of New York, Second Department.

November 23, 1992


Ordered that the order and judgment is affirmed, with costs.

Lien Law § 11 requires a party to serve a notice of lien on the owner, and expressly states that failure to file proof of service within 35 days after the notice of lien is filed shall terminate the notice as a lien. Since the appellant failed to file proof of service as required by the clear and unambiguous language of the statute, the Supreme Court properly granted the petition to vacate the lien...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases