Order unanimously affirmed without costs.
Memorandum:
We reject plaintiff's contention that issues of fact exist regarding whether the interim completion dates identified in the construction schedule of the parties' contract were material elements of that contract and whether time was of the essence regarding each interim completion date. We conclude that the clear and unambiguous language of the contract demonstrates that adherence to the interim completion...