Ordered that the order and judgment is modified by deleting the first, second, third, fourth and seventh decretal paragraphs thereof and substituting therefor a provision denying the defendants' motion for summary judgment; as so modified, the order and judgment is affirmed insofar as appealed from, with costs to the plaintiff.
Contending that the plaintiff failed to comply with the 75% conversion requirement within the time specified, the defendants sought to terminate the lease, whereupon the plaintiff commenced this action, inter alia, for a declaration that "conversion" had been effectuated and that therefore the defendants had no right to terminate the lease. On a motion and cross motion for summary judgment, the Supreme Court declared that although warehouse use had been discontinued throughout the building and although the plaintiff obtained a temporary certificate of completion for the building for business office use, the conversion requirement had not been satisfied because two floors were not "occupiable" by the time specified and that, therefore, the defendants were entitled to terminate the lease.
It is well-settled that determination of the intent of the parties to a contract can be made as a matter of law without trial where that intent is discernible from the four corners of an unambiguously worded agreement (see, Hartford Acc. & Indem. Co. v Wesolowski, 33 N.Y.2d 169; Ligator v Continental Bank, 152 A.D.2d 684, 685). Where, however, the language of a contract is susceptible of varying but reasonable interpretations, the parties may submit extrinsic evidence as an aid in construction, and the resolution of the ambiguity is for the trier of fact (see, State of New York v Home Indem. Co., 66 N.Y.2d 669). We find that whether the parties here intended that the building was to be ready for occupants by March 20,
In light of the foregoing, it is unnecessary to reach the parties' remaining contentions.
Comment
User Comments