LOBRANO, Judge.
The sole issue in the case is whether the trial court erred in dismissing plaintiff's suit for a preliminary injunction upon plaintiff's ex parte motion, where defendant in his answer had asked for damages and attorney fees.
The underlying facts are as follows: Smoyer Construction Co., plaintiff and Hamrick Supply Co., defendant entered into a contract on August 28, 1986, under which Hamrick was to install and furnish "dry walling" at 3601...