MARVIN, Judge.
The plaintiff utility contractor appeals a judgment rejecting its demand against the water district for the $5,600 balance owed on a contract for extending water lines. The issues relate to the admissibility and sufficiency of evidence and as to why the $5,600 was not paid. We reverse and render judgment in favor of plaintiff utility contractor.
FACTS
The contract, signed in 1981, required the work to be completed by April 30, 1982...