LESLIE, Judge.
The buyers of several townhouses sued the sellers when they were unable to close on the dates specified in their respective purchase agreements, due to delays in construction. The trial court awarded the buyers damages caused by the increase in interest rates between the time of the originally scheduled closings and the actual closing dates. The sellers have appealed. We affirm.
FACTS
In 1983 the respondents ("buyers...