Plaintiff, a painting contractor, was awarded a subcontract to do the painting in connection with a project to construct a mill for Seaboard Allied Mill in the City of Albany. Part of the subcontract involved painting the interior of 36 concrete silos. The contract price for this portion of the subcontract was $34,000. Bid specifications required that blue resin epoxy paint be applied over white primer or sealer. Federal regulations required the final coat of blue resin epoxy...