HUBBELL, Chief Justice.
After submitting a low bid of $239,975.00, appellee, West-Ark Construction Co., was awarded a contract to build an apartment project for appellants, Don Sellers and Carl Winn. The appellants had paid $25,000.00 for the project site and had obtained a loan to build the project from Farmers Home Administration in the amount of $260,000.00. Appellee completed the construction and was paid during the course of construction $239,975.00 plus $8,275...