Plaintiff has moved and defendant has cross-moved for summary judgment with respect to a contractual provision dealing with reimbursement for counsel fees and other expenses on the conditions set forth.
Defendant 805 Third Avenue Co., was in 1979, proposing to construct a major office building on a site at 805 Third Avenue between 49th and 50th Streets in the City of New York. In order to obtain greater rentable area,...