LYNCH, J.
This is an action brought by tenants of the Heritage Elderly Housing Project (Heritage), located in East Boston, against the developer and the general contractor for the project. The named plaintiffs seek, on behalf of themselves and all other tenants of Heritage,
The plaintiffs' complaint, filed September 30, 1980, is in five counts. In two of the counts the plaintiffs contend that the defendant Lidapell Corporation, Inc. (Lidapell) (1) negligently breached a duty it owed to the plaintiffs to design a watertight building, and (2) breached express and implied warranties that the building, as designed, would be free of substantial defects. In the three remaining counts, the plaintiffs allege that the defendant Peabody Construction Co., Inc. (Peabody), (1) negligently breached a duty it owed to the plaintiffs to construct a watertight building, (2) made subsequent repairs to the building in a negligent manner, and (3) breached express and implied warranties that the completed building would be free of substantial defects. The plaintiffs also alleged that Lidapell had intentionally concealed the existence of latent design and construction defects and that Peabody had either concealed construction defects or, in the alternative, had made efforts at repairing
The relevant factual allegations of the complaint can be summarized as follows. Heritage is a 301-unit housing complex for elderly persons and is currently owned and operated by the Boston Housing Authority (BHA). The plaintiffs White and Ferrara have lived in Heritage apartments since September 1, 1975, and October 1, 1975, respectively. Heritage was developed and originally owned by the defendant Lidapell and was sold to the BHA in October, 1975, as part of the federally subsidized "turnkey" program.
Lidapell and Peabody both moved to dismiss the complaint for failure to state a claim upon which relief can be granted. Mass. R. Civ. P. 12 (b) (6), 365 Mass. 754 (1974). In relevant part these motions raised the statute of limitations (G.L.c. 260, § 2B) as a bar to the negligence counts and lack of privity as a bar to the warranty counts. Peabody attached to its motion a copy of one of the contracts executed by Peabody and Lidapell, as well as the affidavit of Peabody's president attesting to the genuineness of the copy. Both defendants filed supporting briefs, as required
Counsel for all parties argued the motions before a Superior Court judge at a hearing held on January 13, 1981. During the oral argument, counsel for the plaintiffs conceded that the water leaks had begun "immediately," i.e., as soon as the named plaintiffs moved into Heritage on September 1 and October 1, 1975. On February 6, 1981, the judge issued a decision ordering the complaint dismissed as untimely under the three-year limitations period of G.L.c. 260, § 2B. The judge stated in his decision that he had treated the motion as one for summary judgment because he had considered the statement of the plaintiffs' counsel at oral argument, a matter outside the complaint, in reaching his decision. See Mass. R. Civ. P. 12 (b), 365 Mass. 754 (1974). The judge noted the plaintiffs' allegations of fraudulent concealment and justified late discovery of the claim but found these theories "inapposite" in light of the admission that the leaks began in 1975. He concluded that the plaintiffs' cause of action accrued at that time, making 1978 the last year in which a complaint could seasonably have been filed. Final judgment was entered in favor of the defendants on February 10, 1981.
On February 20, 1981, the plaintiffs filed a motion pursuant to Mass. R. Civ. P. 59 (e), 365 Mass. 827 (1974), to alter or amend the judgment, so as to reinstate the warranty counts of the complaint or to clarify the reasons for dismissal of these counts. The plaintiffs gave as grounds for the motion that the defendants' motion to dismiss had raised the statute of limitations only with respect to the negligence counts. On February 27, 1981, the plaintiffs filed a "motion for relief from judgment or order," see Mass. R. Civ. P.
All three of the plaintiffs' postjudgment motions were denied on March 4, 1981, by the same judge who had earlier dismissed the complaint. The judge found the warranty counts barred by the statute of limitations and reiterated his previous ruling that the claim of fraudulent concealment was irrelevant on the facts of the case. The plaintiffs appealed from the judgment of dismissal and from the order denying the postjudgment motions, and we granted their application for direct appellate review. We affirm the judgment of dismissal.
The judge handled the defendants' motions as motions for summary judgment because, in reaching his decision, he considered the statement of the plaintiffs' counsel at oral argument that the leaks began "immediately." We assume, as the judge apparently did, that this admission was a matter "outside the pleading ... presented to ... the court" within the meaning of rule 12 (b),
It is undisputed that the judge did not expressly notify the parties in this case of his intention to treat the defendants' motions under rule 56. As a general rule, it is important that the parties to an action receive notice of the judge's decision to proceed under rule 56, and many courts have found reversible error where the trial judge failed to give notice. 2A Moore's Federal Practice par. 12.09 [3], at 2302 n. 25 (2d ed. 1982 & Supp. 1981-1982), and cases cited. 5 C.A. Wright & A.R. Miller, Federal Practice and Procedure § 1366, at 683 & n. 72 (1969 & Supp. 1981). See Capodilupo v. Petringa, 5 Mass.App.Ct. 893, 894 (1977). The purpose of notice is to ensure that neither party is taken by surprise by the judge's reliance on material outside the pleadings and thereby deprived of an opportunity to present further material in response. Moore's Federal Practice, supra at 2302 n. 25. C.A. Wright & A.R. Miller, supra at 683.
We fail to see how the plaintiffs in this case could have been unfairly surprised by the judge's use of the information furnished by their own counsel as to when the leaks began. The defendants' motion put them on notice that the statute of limitations would be an issue at the hearing. The judge's question could not have been unexpected. See Dayco Corp. v. Goodyear Tire & Rubber Co., 523 F.2d 389, 393 (6th Cir.1975) (no unfair surprise where notice of conversion would merely have informed parties of what they should already have known). This is not a case where the judge effected a conversion of a rule 12 (b) (6) motion to a rule 56 motion by relying on statements in an affidavit submitted by the moving party without affording the nonmoving party the opportunity to submit counter affidavits.
We have concluded that, as a practical matter, the plaintiffs have not been prejudiced by the failure of the judge to comply with the notice requirements of rule 12 (b) (6) and rule 56. See Melanson v. Caribou Reefers, Ltd., 667 F.2d 213, 214 (1st Cir.1981); Dayco Corp. v. Goodyear Tire & Rubber Co., supra at 392-393. We therefore turn to our underlying conclusion that summary judgment under rule 56 was appropriate because there is no genuine issue as to any material fact, and thus the defendants are entitled to judgment as a matter of law.
2. Statute of limitations for negligence counts. All parties agree that the statute of limitations applicable to the plaintiffs' negligence counts is G.L.c. 260, § 2B, as amended by St. 1973, c. 777, § 2, which reads: "Actions of tort for damages arising out of any deficiency or neglect in the design, planning, construction or general administration of an improvement to real property shall be commenced only within three years next after the cause of action accrues; provided, however, that in no event shall such actions be commenced more than six years after the performance or furnishing of such design, planning, construction or general administration."
The determination of when a cause of action "accrues" has generally been left to the courts by the Legislature. Franklin v. Albert, 381 Mass. 611, 617 (1980). Cannon
If the plaintiffs' causes of action in negligence accrued in 1975 (when they moved into their apartments), their action, brought in 1980, is barred by G.L.c. 260, § 2B. To avoid this result, the plaintiffs seek to bring themselves within the so called discovery rule under which certain causes of action based on inherently unknowable wrongs do not accrue until the plaintiff learns, or reasonably should have learned, that he has been harmed by the defendant's conduct. This rule has been applied in a variety of settings. See, e.g., Franklin v. Albert, supra (medical malpractice); Friedman v. Jablonski, 371 Mass. 482 (1976) (deceit in sale of real estate); Hendrickson v. Sears, 365 Mass. 83 (1974) (negligent certification of title to real estate by attorney).
The language of G.L.c. 260, § 2B, clearly establishes some variant of the discovery rule for design and construction negligence cases. See Hendrickson v. Sears, supra at 89. We think the judge correctly held, however, that delayed discovery principles are not involved in this case. The plaintiffs admitted at oral argument and reiterate in their brief in this court that the building planned and constructed by the defendants was "plagued with serious leakage from its inception." This situation was sufficient to put them on notice that they were being injured.
The plaintiffs argue that their causes of action did not accrue until July, 1980, when "the cause of [and] cure for" the leaks had been "finally determined" by the BHA and the BHA had reported its findings to the plaintiffs' attorney.
In all of the delayed discovery cases cited above, the nature of the defendant's wrong was such that the plaintiff did not discover and could not reasonably have discovered that he or she had been injured until the limitations period, measured from the date the injury actually occurred, had already expired. The plaintiffs here knew they were injured in 1975. They should reasonably have known that widespread water leaks in a newly constructed building are almost certainly the result of design or construction defects. The building was a public project and the identity of its designer and builder were matters of public record. There was, in short, nothing inherently unknowable about these causes of action. Mansfield v. GAF Corp., 5 Mass.App.Ct. 551, 555 (1977) (cause of action for leaky roof accrues when leaks discovered, not when plaintiff later learns no satisfactory repair is possible). In the circumstances of the case before us, the three-year limitations period began to run in 1975 and expired in 1978, well before the plaintiffs' complaint was filed in 1980.
We note that one of the negligence counts of the plaintiffs' complaint alleged that the defendant Peabody undertook to repair the leaks at the Heritage project and did so in a negligent manner. It is possible that some of this repair work was performed less than three years before the action was filed. However, the plaintiffs have made no separate argument addressed to the timeliness of this count. Further, and more importantly, there is no allegation that any
3. Statute of limitations for warranty counts. The plaintiffs argue that their complaint was timely under G.L.c. 106, § 2-318, as amended through St. 1974, c. 153.
General Laws c. 106, § 2-105, inserted by St. 1957, c. 765, § 1, defines "goods" as "all things ... which are movable at the time of identification to the contract for sale." The contract between Lidapell and Peabody called for "[t]he erection of buildings" and the contract between Lidapell and the BHA was for the sale of a completed building. The wrongs alleged in the plaintiffs' complaint are defective "design" and "construction" of a building by the defendants. Neither of the underlying contracts was for the sale of movable things, although "goods" obviously played
The plaintiffs have cited no case holding that a contract for the construction or sale of a completed building is a sale of goods.
In sum, no transaction in goods (G.L.c. 106, § 2-102) sufficient to bring the plaintiffs' action under art. 2 has been shown.
4. Fraudulent concealment and equitable estoppel. The plaintiffs maintain that, even if their cause of action accrued when the leaks first occurred, a factual issue exists (or could be shown to exist if further discovery were allowed) as to whether the defendants fraudulently concealed the cause of action. They contend summary judgment is therefore inappropriate. In making this argument, the plaintiffs assume again that there is a material distinction between knowledge of the leaks and knowledge that the specific causes of the leaks were design and construction deficiencies in the building.
"In the absence of a fiduciary duty of full disclosure, the period of limitations was not tolled under G.L.c. 260, § 12 [the Massachusetts fraudulent concealment statute], unless the defendant[s] concealed the existence of a cause of action through some affirmative act done with intent to deceive. Stetson v. French, 321 Mass. [195, 198 (1947)], and cases cited." Frank Cooke, Inc. v. Hurwitz, 10 Mass.App.Ct. 99, 108 (1980). See also Lynch v. Signal Fin. Co., 367 Mass. 503, 507 (1975). "[A] cause of action is not concealed from one who has knowledge of the facts that create it." Stetson v. French, supra. By their own admission, the plaintiffs were aware of the leaks in 1975. In their brief they characterize their building as containing "an extraordinary number of leaks from the time of the initial occupancy," and they point to material establishing that they complained to the BHA about the leaks "regularly from 1975
The plaintiffs suggest that the defendants undertook "superficial waterproofing repairs, affirmatively attempting to mask the true cause of the leaks." Even assuming the truth of this allegation, the repair efforts did not succeed in concealing from the plaintiffs their cause of action and, in any event, should have had the effect of removing any doubts as to the identity of those responsible for the plaintiffs' injuries.
The plaintiffs argue, in the alternative, that the defendants should be estopped from raising the statute of limitations "because of their conduct in continuing to represent that the problem would be solved by waterproofing." It appears that this theory is being raised for the first time in this court. No facts relevant to this issue are alleged in the complaint, although facts suggesting fraudulent concealment are alleged. Furthermore, no mention of it is made in the judge's opinions, although fraudulent concealment and delayed accrual are discussed (and found to be irrelevant). The plaintiffs have no right to have this issue considered for the first time on appeal.
In any event, estoppel would require proof that the defendants made representations they knew or should have known would induce the plaintiffs to put off bringing a suit and that the plaintiffs did in fact delay in reliance on the representations. See, e.g., LaBonte v. New York, N.H & H.R.R., 341 Mass. 127, 131 (1960); MacKeen v. Kasinskas,
We conclude that the plaintiffs' claims are time-barred and that, in the circumstances, none of the information which the plaintiffs seek a continuance to discover could remove this bar. The defendants were therefore entitled to judgment as a matter of law.
Judgment affirmed.