NESBITT, Judge.
The issue before us is whether a materialman may recover against a surety on a construction bond absent compliance with a condition precedent requiring written notice be given within ninety days after the claimant has furnished the materials for which the claim is made. We hold that the materialman's failure to comply with the notice provision of the bond precludes recovery and reverse the judgment of the trial court.
In 1977, appellee, National...