SAM D. JOHNSON, Circuit Judge:
The Federal Energy Regulatory Commission (FERC) in the orders under review provided that natural gas producers holding "optional procedure" certificates under 18 C.F.R. § 2.75 could not seek the new, higher ceiling rates under the Natural Gas Policy Act of 1978 (NGPA), 15 U.S.C.A. §§ 3301-3432. Petitioners seek review of these FERC orders. Because this Court finds that FERC based its order on a proper interpretation of the NGPA, its own regulations, and the conditions imposed on the certificate granting petitioner Columbia Gas Development Corporation authority to sell its gas in interstate commerce, the Commission's orders are accordingly affirmed.
I. Background and Facts
Under the Natural Gas Act of 1938 (NGA), 15 U.S.C.A. §§ 717-717w, interstate sales of natural gas were regulated in a three-fold manner. First, a certificate of public convenience and necessity was required to enter the interstate market. NGA § 7(c) and (e), id. § 717f(c), (e). Second, the price at which interstate gas could be sold must have been "just and reasonable." NGA §§ 4(a), 5(a), id. §§ 717c(a), 717d(a). Finally, Commission approval was necessary for any change in a contract price for gas. No change in price, or in any of the terms of the certificated contract, could be effected unless the seller gave thirty days notice to the Commission and to the public. NGA § 4, id. § 717c(d), (e). During that thirty-day period, the Commission could suspend the proposed rate increase for up to five months to determine whether the new rate was just and reasonable. If after five months the Commission had not made that determination, the proposed rate increase became effective automatically; the Commission still retained the power, however, to disallow the increase in the event it found the new rate not to be just and reasonable. The seller was then required to refund to its buyers any revenues it collected as a result of the new rates that were in excess of what was determined to be just and reasonable. See generally Freeport Oil Co. v. FERC, 638 F.2d 702, 703-05 (5th Cir. 1980).
For the most part the Commission set ceiling rates for producer sales on an area, and then later on a nationwide, basis. These "just and reasonable" area or national ceiling rates became the benchmark for
One of these efforts was 18 C.F.R. § 2.75, Optional Procedure for Certificating New Producer Sales of Natural Gas.
In return for obtaining under the optional procedure the benefit of increased certainty and a higher price, 18 C.F.R. § 2.75(m)(1) provided that, upon acceptance of a certificate issued under the optional procedure, the seller unconditionally agreed to "waive all rights to seek future rate increases under Section 4 of the Natural Gas Act with respect to the contracts submitted, other than price escalations, if any, as certificated by the Commission."
On November 9, 1978, the NGPA became law. Its pricing and certain other provisions extend to all interstate and intrastate sales of natural gas on or after December 1, 1978. NGPA § 101(b)(4), id. § 3311(b)(4). Title I of the NGPA establishes the ceiling price structure for producer sales of natural gas. Petitioners seek to charge rates under two of those pricing provisions — sections 102(d) and 104, id. §§ 3312(d), 3314.
Both of these pricing provisions involve gas that is "committed or dedicated to interstate commerce" within the meaning of the NGPA. Section 102(d) applies to gas produced from newly discovered reservoirs under old leases on the Outer Continental Shelf. Section 104 applies to natural gas "committed or dedicated in interstate commerce"
In the interim regulations implementing the NGPA, and in Order Nos. 64 and 64-A,
A producer holding an optional procedure certificate and whose gas remains subject to the NGA can only petition the Commission for special relief, on an individual basis, removing the waiver condition.
Petitioner Columbia Gas Development not only participated with the other petitioners in the administrative process resulting in Order Nos. 64 and 64-A, it filed contract amendments, to collect any higher ceiling prices, for certain gas currently under optional procedure certificates, and made a blanket affidavit filing
II. The Scope of the Optional Procedure Certificate Waiver In Section 2.75(m)(1)
The first issue in this case is whether or not the language of the regulation requires
Section 2.75(m)(1), the crux of the dispute in this case, provides that "[b]y acceptance of a certificate issued hereunder, the seller-applicant unconditionally agrees to (1) waive all rights to seek future rate increases under Section 4 of the Natural Gas Act with respect to the contract submitted, other than price escalations, if any, as certificated by the Commission ...." Section 2.75(f) provides that no contract would be accepted for filing under the optional procedure if the contract included "any type of indefinite pricing clause" other than "BTU price adjustment clauses, clauses to reflect changes in state production taxes and clauses allowing for the recovery of compression and dehydration charges." Area rate clauses are expressly included within indefinite pricing clauses under this regulation. Therefore, contracts could be certificated with fixed (definite) escalation clauses and the three specified types of indefinite escalation clauses dealing with certain direct operating cost and gas quality changes.
The Commission interprets the regulation to waive all rights under NGA § 4 to seek any and all future rate increases (with the exception of certificated escalation clauses as specified in section 2.75(f)). The petitioners' position would rewrite the regulation to waive "all rights to seek future Natural Gas Act rate increases." In other words, the Commission's focus is on the filing procedure, while the petitioners' is on the type of rates. These two interpretations are possible because the phrase "under Section 4" could modify either "all rights" or "rate increases." The question this case presents us is which of these two meanings does the regulation have?
An agency's interpretation of its own regulation is entitled to great deference. Udall v. Tallman, 380 U.S. 1, 16, 85 S.Ct. 792, 801, 13 L.Ed.2d 616 (1965). Administrative regulations such as this one are to be interpreted broadly and liberally to effectuate their central purposes. Pennzoil Co. v. FERC, 645 F.2d 360, 383 (5th Cir. 1981); Baldridge v. Hadley, 491 F.2d 859, 864 n.2 (10th Cir.), cert. denied, 417 U.S. 910, 94 S.Ct. 2608, 41 L.Ed.2d 214 (1974). This Court holds that FERC's interpretation of section 2.75(m)(1) as a waiver of the general right to make rate increase filings, which precludes the collection of NGPA ceiling prices, is not plainly erroneous, United States v. Larionoff, 431 U.S. 864, 872, 97 S.Ct. 2150, 2155, 53 L.Ed.2d 48 (1977), clearly unreasonable, Homan & Crimen, Inc. v. Harris, 626 F.2d 1201, 1208-09 (5th Cir. 1980), or inconsistent with the statute under which it was promulgated, Larionoff, 431 U.S. at 873, 97 S.Ct. at 2156. This Court does so on the basis of the purpose of the optional procedure within the context of the regulatory scheme in which it was promulgated, the purpose and language of the waiver, and the use of the waiver in the face of changed regulatory circumstances.
The provision of the optional procedure was in recognition that certain higher cost gas supply projects required an interstate market rate greater than what was currently available. The Commission therefore provided the producer the opportunity for an individual price determination as an alternative to ceiling prices of general applicability. The purpose of the waiver, including the waiver of the right to make rate increase filings pursuant to an area rate clause, was that the optional procedure should not just be an option that the producer could switch back and forth between with general ceiling prices, whichever was most beneficial at any given time. Instead, it was made a binding alternative to general ceiling price regulation; producers were prevented from collecting general ceiling prices when those general ceilings were increased to a level above the certificated individual price.
Making the option a binding alternative was prudent and fair economic policy. As a rational economic person, the producer looked at future expected production, future expected costs, and determined what the future expected revenues would have to
Use of the waiver prior to the NGPA supports the view that the waiver was intended to broadly waive future rate increases. In Ecee, Inc. v. FPC, 526 F.2d 1270 (5th Cir.), cert. denied, 429 U.S. 867, 97 S.Ct. 176, 50 L.Ed.2d 147 (1976), one question was whether the scope of the waiver was broad enough to preclude filings for the new FPC national ceiling rates, which were higher than the prevailing FPC area ceiling rates. This Court upheld the Commission's position that the waiver precluded collection of the national ceiling rates. See also Public Service Commission v. FERC, 589 F.2d 542, 561-62 (D.C.Cir.1978).
Both the national ceiling rates and the NGPA ceiling prices are ceiling rates of general applicability. Pennzoil v. FERC, 645 F.2d 360, 382 (5th Cir. 1981). The Commission's past flexible use of the waivers to broadly encompass national ceiling rates justifies a similar flexible reading to encompass NGPA ceiling rates. As with the FPC regulation dealing with area rate clauses, the intent of the optional procedure waiver condition seems to have been to deal with federal ceiling prices, and not with a particular type of price (NGA rates) or a ceiling price from a particular source (Commission-prescribed rates). See generally Pennzoil, 645 F.2d at 382-83. Accordingly, a holder of an optional procedure certificate whose gas remains within NGA jurisdiction is precluded under that certificate from making a rate increase filing pursuant to NGA § 4. He may collect only the optional procedure rate, which precludes collection of any higher ceiling price, including any inflation adjustment under section 104.
III. The Scope of the Waiver in Columbia's Optional Procedure Certificate
Petitioner Columbia additionally argues that its particular certificates are conditioned with a waiver expressly limited to price increases authorized by the Commission in area or national rate proceedings under the NGA. It further argues that the express condition language embodies the scope and intent of section 2.75(m)(1).
Columbia's optional procedure certificates were subject to express conditions imposed by an Administrative Law Judge (ALJ) and approved by the Commission. The ALJ's initial decision in part provided:
Specific language concerning waiver of the right to file for future rate increases ordinarily was not necessary because acceptance of the certificate constituted unconditional agreement to the section 2.75(m)(1) waiver. These conditions were imposed because Columbia's contracts contained area rate clauses, an indefinite pricing clause that section 2.75(f) designated as impermissible for contracts submitted under the optional procedure. These contracts were accepted for filing because Columbia and the other applicants involved agreed to waive the operation of those clauses.
Like an agency's interpretation of its own regulation, an agency interpretation of conditions imposed by the agency on a certificate holder is entitled to deference on judicial review and will be overturned only if arbitrary, capricious, or clearly erroneous. See Seaboard Coast Line Railroad v. United States, 599 F.2d 650, 652 (5th Cir. 1979); Chem-Haulers, Inc. v. ICC, 594 F.2d 166, 168 (5th Cir. 1979). This Court upholds the Commission's interpretation of Columbia's certificate conditions as disallowing any future filings for rate increases.
Columbia's argument relies on the ALJ's explicit reference to increases in area or national rates. Section 2.75(m)(1) does not contain any similar reference. As with area rate clauses, references in certificates to area or national rates should not be literally and strictly limited to ceiling prices promulgated by the Commission under the NGA, but instead should be flexibility interpreted to include federal ceiling prices of general applicability, whether prescribed by Congress or the Commission, unless persuasive evidence of a narrower intent shows otherwise. See Pennzoil, 645 F.2d at 389-90 (reference to area rates can reasonably be interpreted to mean ceiling rates of general applicability). See also Coca-Cola Co. v. Atchison, T. & S. F. Railway, 608 F.2d 213, 221 (5th Cir. 1979) (strict construction against drafter of tariff not justified if it ignores an alternative, reasonable construction that conforms to practical application and the intent of the drafters).
In this case, the evidence persuades this Court that the ALJ's condition, like the waiver condition in section 2.75(m)(1), encompasses federal ceiling prices generally. The Commission approved the ALJ's finding that, as conditioned, the certificates applied for would be "in conformity with section 4 of the Natural Gas Act ... and the regulations of the Commission thereunder, 18 CFR § 2.75." Therefore, the discussion in part II of this opinion concerning the intended scope of the section 2.75(m)(1) equally applies to the ALJ's specific condition.
Columbia also relies on the ALJ's language that the condition would terminate and be of no force and effect if the Commission amended its regulations to authorize the otherwise prohibited price increases. This proviso was necessary so that the certificate holder could take advantage of any Commission repeal of the section 2.75(m)(1) waiver condition or any congressional repeal of producer rate regulation under the Natural Gas Act. This is similar to applications for optional procedure certificates that often included language that the waiver would be effective during the term of the optional procedure certificate, "absent change in the Commission's Regulations or in the Natural Gas Act." This language would permit the certificate holder to take advantage of any repeal of the optional procedure certificate conditions by either the Commission or Congress. Contrary to the thrust of petitioners' argument, it cannot undo the conditions simply because of any changes in Commission regulations or the statutory framework, no matter how unrelated to the certificate conditions those changes may be. This brings us to the second major issue in this case — the effect of the NGPA.
IV. The NGPA and Optional Procedure Certificate Waivers
Petitioners argue that the NGPA repeals either the optional procedure certificate waiver condition for existing certificates or the NGA § 4 filing requirement. Petitioners' initial argument runs as follows. NGPA §§ 102(d) and 104 prescribe maximum lawful inflation-adjusted prices that "shall apply" to sales of gas qualifying under those respective sections. NGPA § 101(b)(5) provides that if any gas qualifies under more than one NGPA pricing section or exemption from price ceilings, "the provision which could result in the highest price shall be applicable." Petitioners point to the language "shall apply" in the pricing sections and the language "shall be applicable" in section 101(b)(5). They maintain that this "mandatory language" repeals the waiver condition with regard to optional procedure gas that could qualify for section 102(d), and permits collection of at least the inflation adjustment for optional procedure gas that does not so qualify and therefore remains under section 104.
Petitioners further argue that even if the NGPA does not repeal the waiver condition, it repeals, or at least reduces to an empty formality, the requirement that a seller subject to the Commission's jurisdiction under the NGA must make a rate increase filing pursuant to NGA § 4(d) to collect a higher rate. The crux of this argument is that the purpose of the filing requirement is to enable the Commission to determine the lawfulness of the proposed rate increase, and since NGPA § 601(b) deems its statutory ceiling prices to be just and reasonable for purposes of the NGA, there is nothing left for the Commission to decide.
As with agency interpretations of its own regulation or certificates issued by it, an agency's interpretation of its own statute is generally given deference, Udall v. Tallman, 380 U.S. 1, 16, 85 S.Ct. 792, 801, 13 L.Ed.2d 616 (1963), unless that interpretation is clearly wrong or unreasonable, Coca-Cola Co. v. Atchison, T. & S.F. Railway, 608 F.2d 213, 222 (5th Cir. 1979). This Court concludes that FERC's interpretation — that the NGPA repeals neither the waiver condition for existing certificates nor the NGA § 4 filing requirement — is not clearly wrong or unreasonable.
Contrary to petitioners' argument, congressional prescription of ceiling prices for
Petitioners argue that it is inappropriate to distinguish between qualifying for a particular price under the NGPA and collection of that price. They point to NGPA § 101(b)(9) as the only exception to the otherwise mandatory requirement in section 101(b)(5) that the highest maximum lawful price that the gas can qualify for is the applicable maximum lawful price for that gas. Petitioners are in effect invoking that hoary maxim of statutory interpretation expressio unius est exclusio alterius, that is, statutory specification of one exception to a general rule excludes other exceptions not expressed.
This maxim has no application in this case because section 101(b)(9) is merely a corollary to the concept of the ceiling price. See Pennzoil, 645 F.2d at 374, 375. The significance of section 101(b)(5) is that the highest ceiling the gas qualifies for will be the applicable ceiling, and thus is merely a rule of construction when gas qualifies for more than one category. The establishment of ceilings, including the establishment of a particular ceiling among a choice of applicable ceilings, does not constitute authority to collect the ceiling price. See Pennzoil, 645 F.2d at 379-80.
Petitioners also argue that the waiver condition is a "pricing condition" or "pricing regulation" inconsistent with the NGPA and therefore is superseded by the operation of the NGPA. It is true that the optional procedure was a price-setting mechanism, and, as with all of the Commission's other producer price-setting mechanisms under the NGA, has been displaced by the NGPA so that optional procedure certificates are no longer being issued by the Commission. Existing certificates, that is, optional procedure certificates issued prior to the NGPA, present an entirely different question.
NGPA § 104 incorporates by reference and carries forward prior FPC price regulation. The optional procedure was one such pricing approach; therefore, the certificated price in an optional procedure certificate is that certificate holder's initial section 104 ceiling price. Section 104 provides that its ceiling price is to be adjusted monthly by an inflation factor. Since section 104 gas remains subject to NGA jurisdiction, the optional procedure certificate holder is unable to collect the ever-increasing section 104 ceiling price because he is disabled from making the requisite NGA § 4 rate increase filing necessary to lawfully collect a price higher than the certificated price.
This Court therefore holds that the NGPA does not repeal the waiver condition for existing optional procedure certificates. This brings us to the question of whether the NGPA expressly or impliedly repeals the NGA § 4 rate increase filing requirement.
There is, of course, no express repeal of the filing requirement itself. The NGPA never mentions the NGA § 4 filing requirement. The only express repeal possible is for gas that formerly was but now is no longer subject to NGA jurisdiction, pursuant to section 601(a)(1). In essence, NGPA § 601 curtails NGA jurisdiction, and then preserves and maintains that curtailed NGA jurisdiction.
Aside from the elimination of the filing requirement for gas removed by section 601 from NGA jurisdiction, there is no express repeal of the NGA filing requirement for optional procedure certificate gas that remains within NGA jurisdiction. See Pennzoil, 645 F.2d at 380-82, 390, 393 (recognizing that NGA § 4 continues to apply to gas not qualifying for NGPA § 601(a)(1)). That leaves the issue of implied repeal.
Repeal by implication arises when there is a plain repugnancy between the operation of two acts or their provisions, but repeals by implication are not favored, and the two acts or provisions thereof are to be given effect consistent with each other whenever possible. See United States v. Tynen, 11 Wall. 88, 78 U.S. 88, 92, 20 L.Ed. 153 (1870). When interpreting and construing two acts that affect one particular subject matter or area, the court must attempt to reconcile the acts, if possible, so as to produce a symmetrical whole. Panhandle Eastern Pipeline Co. v. FPC, 359 F.2d 675, 679 (8th Cir. 1966) (construing NGA with the Helium Act). There is no repugnancy between the NGPA and the NGA § 4 rate change filing requirement. Promulgation of NGPA ceiling prices replaces only the prior FPC ceilings, and does not replace other price-related procedural provisions for gas remaining within NGA jurisdiction.
Petitioners make much of the significance of the filing requirement with regard to Commission rate regulation. They contend that the significance of the NGA § 4(d) filing requirement has been reduced to a perfunctory, information-type filing to inform the Commission that the producer intends to collect the highest NGPA-established rate for which the sale qualifies. In other words, petitioners argue that the NGPA has reduced NGA § 4 to a hollow procedure.
The filing requirement does serve an integral function with regard to rate-setting and rate review for pipeline rate regulation. See generally United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332, 342, 76 S.Ct. 373, 379, 100 L.Ed. 373 (1956). Once the Commission had gotten away from individual producer regulation to
Petitioner Columbia then goes on to argue, however, that FERC has recognized that NGA § 4 has been reduced to nothing more than an administrative notice requirement. It points to FERC Order No. 15,
V. Special Relief from the Optional Procedure Certificate Waiver
Petitioners argue that the Commission is frustrating the incentive purpose of the NGPA. The Commission's position precludes charging the NGPA § 102(d) price for optional procedure gas from new reservoirs on old offshore federal leases. They allege that currently it is economically impossible for a producer to undertake costly offshore drilling at the optional procedure certificate price. It is further alleged that denial of NGPA incentive prices to one or more working interest owners, because that working interest owner is an optional procedure certificate holder, removes potential participants from exploratory offshore drilling enterprise and focuses relatively more risk on the remaining producers as they decide whether to proceed with drilling.
Throughout their briefs petitioners have overbroadly relied on the incentive objective of Congress to support their arguments for wholesale relief from section 2.75(m)(1) — wholesale relief in the sense of convincing this Court that the scope of the waiver is narrow or that the NGPA repeals the waiver or the filing requirement. The NGPA did intend to provide incentives for offshore development. At the same time, the NGPA did not intend indiscriminate application of the incentive. Rather, it reflects a careful balance between two statutory principles: (1) incentive pricing for new gas and price controls on intrastate gas to ensure adequate supplies in the interstate market, and (2) maintenance of NGA price controls on old gas to prevent unnecessary price increases. Note, Legislative History of the Natural Gas Policy Act: Title I, 59 Texas L.Rev. 101, 116 (1980).
Congress recognized that incentives need to be carefully tailored to reach only gas that needs an incentive and should not be available to gas that needs no incentive. See Pennzoil, 645 F.2d at 367, 372; Note, supra, at 119, 124. This was also the basis of the FPC's use of ceiling prices with "vintaging" to prevent windfall profits to holders of older, cheaper reserves,
Although the producer deemed the certificate price sufficient to induce the drilling at the time he sought the certificate, circumstances may have changed so that the certificate pricing condition is frustrating particular development efforts on the Outer Continental Shelf. If an incentive is in fact necessary for a particular project to go forward, specific relief would be appropriate. This relief is available under 18 C.F.R. § 1.7(b), which provides for waivers from any Commission rule or regulation promulgated under the NGA. Under this regulation, a producer could apply to the Commission for removal of the section 2.75(m)(1) waiver condition.
VI. Conclusion
This Court holds that the optional procedure certificate waiver condition precludes such certificate holders from filing for NGPA ceiling prices to the extent that the gas so certificated remains within NGA jurisdiction. Further, this Court holds that the NGPA does not repeal either the NGA § 4(d) filing requirement or the waiver condition for existing certificates. The appropriate avenue for relief from the certificate waiver condition is a petition to FERC under 18 C.F.R. § 1.7. Accordingly, the FERC orders under review are
AFFIRMED.
FootNotes
Columbia and the Pogo, Pennzoil, and Tenneco petitioners further argue that the Commission has unlawfully discriminated against optional procedure certificate holders by allowing producers with gas certificated at area or national rates to collect higher NGPA ceiling prices pursuant to existing or amended contractual authority, and to make a blanket affidavit filing, pursuant to that contractual authority, to collect the NGPA monthly inflation adjustment to the NGPA ceiling prices. They rely on references in certificates to area or national rate regulations to argue that those certificates are conditioned to prohibit collection of any rate in excess of the area or national ceiling rate, and that FERC has unexplainably not claimed that these bar collection of NGPA rates. The certificate is only an authorization to sell, and it is the contract, whose operation may be modified or conditioned upon the issuance of the certificate, that authorizes the collection of prices. The issuance of the optional procedure certificate was conditioned upon waiver of the right to change the rate authorization. Therefore, it is not the certificate itself, but the condition imposed upon its issuance, that differentiates optional procedure certificates from all others. Although petitioners merely assert the existence of these conditions for gas certificated at area or national rates, this Court will assume without deciding that such certificates were conditioned to prohibit collection of rates in excess of the applicable area or national ceiling rate. No discrimination exists, however, because such references are not to be literally and strictly interpreted, but instead, as this Court makes clear in part III of this opinion, infra, should generally be flexibly interpreted to mean federal ceiling prices of general applicability.
Petitioner Texas Gas Exploration also argues that FERC has unlawfully discriminated against optional procedure certificate holders. Texas Gas points to FERC's treatment of minimum rate certificate holders, which in Order No. 64 are permitted to collect the NGPA § 104 inflation adjustment. The minimum rate was an exercise of the Commission's narrow authority to abrogate existing contractual arrangements if the contract price is so low as to adversely affect the public interest, as when it might impair the financial ability of the seller to continue its service, cast upon other consumers an excessive burden, or be unduly discriminatory. In re Permian Basin Area Rate Cases, 390 U.S. 747, 820-22, 88 S.Ct. 1344, 1387-88, 20 L.Ed.2d 312 (1968). This is the only case in which the general rule — that establishment of ceiling prices does not constitute authority to collect the ceiling — does not apply, a very narrow exception based upon unequivocal public necessity. See id.; Pennzoil, 645 F.2d at 379-80. Minimum rates, incorporated and carried forward by NGPA § 104, are adjusted for inflation by the NGPA. Unlike optional procedure gas, minimum rate gas is not precluded from receiving the NGPA inflation adjustment because the minimum rate order provides the authority for its collection.
The Pogo, Pennzoil, and Tenneco petitioners also argue that the Commission has unlawfully discriminated against optional procedure certificate holders whose new offshore reservoir gas qualifies for NGPA § 102(d). Petitioners point to optional procedure certificate holders whose gas qualifies for NGPA § 102(c)(1)(C), which deals with new onshore reservoirs, and who are not denied the § 102 price. The discrimination in this case must be laid at the doorstep of Congress. Section 601(a)(1)(B) removes from NGA jurisdiction gas that qualifies for NGPA § 102(c), but does not remove gas qualifying for § 102(d). Such discrimination may be a relevant factor for the Commission's decision to grant or deny specific relief under 18 C.F.R. § 1.7 from the waiver condition, but it does not show that the Commission is acting arbitrarily or capriciously.
Petitioner Columbia argues that NGPA § 601 simply preserves the NGA requirement that prior to cessation of dedicated gas deliveries the producer must seek abandonment authority and that conditions of service be maintained. The only support given for this assertion is that § 601 refers only to NGA § 1(b) and fails to refer to NGA §§ 4 and 5, which deal with pricing. Section 601, however, also does not refer to NGA § 7, which deals with certification and abandonment. Columbia erroneously states that NGA §§ 4 and 5 deal with pricing jurisdiction, when they in fact deal with pricing authority for gas over which the Commission has jurisdiction under NGA § 1(b). Accordingly, § 601 limits only FERC jurisdiction under NGA § 1(b), and it requires some other limitation in the NGPA to circumscribe or replace FERC's authority under the NGA to regulate gas remaining within its NGA jurisdiction. Columbia's argument that the "vestiges" of NGA regulation under NGPA § 601 are limited to maintenance of dedicated service therefore cannot stand. Price-setting and price-related provisions must be repealed by some other provision. As a price-related provision, the NGA filing requirement is not displaced by the NGPA's price-setting provisions. Nor does the NGPA provide any other provisions that would displace the filing requirement. Therefore, while the NGPA supersedes the continued availability of the optional pricing procedure for new gas, it does not displace all price-related provisions in the NGA, nor for that matter the optional procedure waiver for existing certificates.
Petitioners also argue that because the basic circumstances surrounding the "bargain" between optional procedure certificate holders and the Commission were materially and substantially changed by NGPA producer pricing, the producers should no longer be bound by the old bargain that does not fit the new circumstances. This argument must fail. The NGPA does not materially change the circumstances in which the "bargain" is being performed. The NGPA instead continues price ceilings with "vintaging" to prevent windfall profits to holders of older, cheaper reserves. Pennzoil, 645 F.2d at 372. A contract should be interpreted in light of the changed circumstances to accomplish what the parties intended. Pennzoil, 645 F.2d at 388. The parties intended that the individual producer receive a firm, individual price for his gas as an alternative to general price ceilings. The intention of the parties to prevent switching to general price ceilings is effectuated by preventing optional procedure certificate holders still subject to the NGA § 4 rate change filing requirement from collecting higher NGPA ceiling prices absent relief under 18 C.F.R. § 1.7 from the waiver condition.
Some concern was expressed in comments to FERC that given the views expressed in Order No. 64, the Commission had prejudged § 1.7 petitions and would not grant them. FERC responded in Order No. 64-A with a promise to consider the petitions on their merits. This Court has every confidence that FERC will give due consideration to all petitions, and dispose of them on a rational basis consistent with the dual incentive and windfall prevention goals of the NGPA, in accordance with that promise.
The Pogo, Pennzoil, and Tenneco petitioners argue that because the § 102(d) price is available only for new reservoirs on old offshore leases, the gas by definition needs the incentive. Section 102(d), however, applies to gas produced from a reservoir that was not discovered, that is, not penetrated and capable of producing in paying quantities or commercially producible, before July 27, 1976. It is therefore possible that some gas qualifying for § 102(d) was already within the package of gas that the optional procedure price was intended to bring forth. Qualifying for § 102(d) pricing is thus not the only fact that the producer must show to the Commission sufficient to justify the relief sought. Each petition will turn on its own facts; therefore, this Court leaves to FERC the determination of what additional facts supporting relief can or should be shown to the Commission. We note only that the goal is to provide relief when the optional procedure certificate pricing condition is in fact frustrating further development.