LARRY G. SMITH, Judge.
The trial court was correct in granting summary judgment denying appellant's mechanics lien claim. All work on the project, and the contract under which appellant commenced the furnishing of labor and materials on the job, post-dated the amendment to Section 713.06, Florida Statutes, effective July 1, 1978. As amended, that section provides that the 45-day notice to the owner, required as a prerequisite to the perfecting of a lien by persons...