PACE CONST. CORP. v. HOUDAILLE INDUS., INC.

60365.

155 Ga. App. 923 (1980)

274 S.E.2d 44

PACE CONSTRUCTION CORPORATION et al v. HOUDAILLE-DUVAL-WRIGHT DIVISION, HOUDAILLE INDUSTRIES, INC.

Court of Appeals of Georgia.

Decided October 1, 1980.


Attorney(s) appearing for the Case

Robert O. Fleming, Jr., Kent P. Smith, for appellants.

John P. MacNaughton, Ira L. Rachelson, for appellee.


BANKE, Judge.

This is a suit by the appellee subcontractor to recover for labor and materials furnished in connection with a construction project. The appellants are the general contractor and the two sureties on the latter's performance bond. They contend that the subcontract contained a mandatory arbitration clause and accordingly moved below for an order "staying discovery and all other judicial proceedings in the instant action until such time as all subcontract...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases