MORRIS, Judge.
The appellant and appellee agree that the crux of the question before this Court is whether McKinney can maintain a cause of action against Meir grounded on negligent performance of its contract with the general contractor, Nello L. Teer, to supervise the excavation caisson shafts. McKinney seeks to recover for the expense of manual excavation in the bell portion of the caisson which he argues exceeded the requirements called for in the plans and specifications...