FINDINGS OF FACT and CONCLUSIONS OF LAW
SAMUEL P. KING, Chief Judge.
Introduction
In 1972, Congress passed the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. §§ 1251-1376 (hereinafter referred to as "FWPCA"). Any person who introduces pollutants into navigable waters must comply with the provisions of the FWPCA, see 33 U.S.C. § 1311(a), or face the severe penalties outlined in 33 U.S.C. § 1319. The Environmental Protection Agency (hereinafter "EPA") administers the FWPCA through the National Pollutant Discharge Elimination System (hereinafter "NPDES") permit program. See 33 U.S.C. § 1342(a).
Defendant Hawaiian Electric Company (hereinafter "HECO") operates a power station at Kahe, Oahu. Five steam electric generating units are in operation at Kahe and three more units are in the planning stage. The Kahe power station supplies approximately 60% of the electric power on the island of Oahu.
In order to cool the generating units HECO pumps water from the ocean through the steam condensers located inside the plant. The ocean water, which rises considerably in temperature, is then discharged back into the ocean. This thermal discharge is classified as a pollutant by the FWPCA, see 33 U.S.C. § 1362(6), thus mandating that HECO obtain an NPDES permit from EPA in order to continue operation of the plant at Kahe.
HECO applied for an NPDES permit on May 17, 1973, and received the permit on May 3, 1975. The Department of Health, State of Hawaii (hereinafter "HDOH") adopted the EPA-issued NPDES permit on August 19, 1975 pursuant to 33 U.S.C. § 1342.
The discharge facility, as presently envisioned, will include the construction of a large, roughly triangular "transit basin" at the shoreline. The basin will permit the transfer of the heated water which is carried from the generating plant by a system of large pipes to several small pipes which will then carry the water into the ocean some 800 feet from shore. Although the small pipes are to be buried beneath the ocean floor, the walls of the transit basin will extend approximately 150 feet into the ocean and rise to a height of seven to ten feet above sea level (mean lower low water).
The walls of the transit basin will intersect a surfing site whose prime importance is that it is extremely well suited for teaching surfing to beginners.
Plaintiff Mahelona frequently surfs at Kahe; plaintiff Yoon is a Honolulu Parks and Recreation Department employee who teaches surfing at Kahe; and the Nanakuli Surf Club is an organization whose members surf at Kahe.
Plaintiffs have sought an injunction against further construction of the discharge facility. Their primary
I. Application of NEPA
NEPA requires an EIS for any "major Federal actions significantly affecting the quality of the human environment." 42 U.S.C. § 4332(2)(C).
EPA argues that even if the Kahe project is a "major federal action significantly affecting the quality of the human environment" it is relieved of any responsibilities it had under NEPA by an exemption in the FWPCA relating to the issuance of certain NPDES permits. This contention will be discussed below.
The role of HDOH is basically irrelevant in determining whether an EIS was required in this case. Since HDOH simply adopted the NPDES permit which had originally been issued to HECO by EPA the question of whether HDOH issuance of an NPDES permit in the first instance would constitute major federal action is not presented by this case.
The Corps makes two arguments to explain its failure to prepare an EIS. First, it argues that the Kahe project will not significantly affect the quality of the human environment.
The Corps' contention that the discharge facility would not have a significant environmental impact, on the record before the court at this time, is rejected. At the outset, it is noted that the Environmental Assessment which the Corps prepared did not explicitly conclude that the construction at Kahe would have no significant impact on the human environment. The Corps only stated, "Although the US Army Corps of Engineers identified environmental concerns which are addressed in the assessment, EPA determined that an environmental statement was not required. The planning, design, and partial construction of the project have progressed to a point where alteration of the plans would be costly to the public and delay completion of urgently needed power plant. Considering the present state of construction, an environmental statement would not be a practical or an effective instrument for disclosure and mitigation of environmental impacts of the proposed action."
This statement hardly amounts to a finding of no significant impact on the human environment; in fact, it almost implies that such an impact can be expected. The court also notes the contrast between this statement and the explicit, albeit dubious, finding in an earlier Environmental Assessment by the Corps regarding the on-shore intake facilities in the Kahe area that no significant environmental consequences could be expected.
To substantiate its claim that there would be no significant environmental impact from the construction of the discharge facility at Kahe, the Corps relies very heavily on the lack of adverse public response to public notices regarding HECO's permit application. In a case such as this, however, where the Corps knows that a project will seriously interfere with an important existing activity in an area, it may not place such reliance on the silence of relatively unorganized and ill-informed citizens in determining the environmental impact of a proposed project. The expression of public concern, or the lack thereof, should be only one of many factors which the Corps considers in determining whether an EIS is required. This burden on the Corps is preferable to risking the substantial and often irreversible environmental and financial consequences which may result from a short-sighted and narrow approach by the Corps to its NEPA responsibilities.
Nothing in this opinion, however, would necessarily operate to prevent the Corps from preparing an adequate Negative Assessment demonstrating that no significant environmental impact will result from construction of the transit basin at Kahe, if that should be the Corps' conclusion after appropriate study of the matter. Cf. Mid-Shiawassee County Concerned Citizens v. Train, 408 F.Supp. 650, 654 (E.D.Mich.1976).
The second ground advanced by the Corps to explain its failure to prepare an EIS is that since EPA is the lead agency
II. Application of the FWPCA Exemptions
A. EPA
EPA and HECO have strenuously argued that the FWPCA exempts EPA from what might otherwise be its obligation to issue an EIS. The defendants rely on 33 U.S.C. § 1371(c)(1) which provides:
There is no dispute that EPA was required to prepare an EIS only if the discharge facility is a "new source". "New source" is defined in 33 U.S.C. § 1316(a)(2) as "any source, the construction of which is
"Source", in turn, is defined as "any building, structure, facility, or installation from which there is or may be the discharge of pollutants." 33 U.S.C. § 1316(a)(3).
While the discharge facility arguably comes within this literal statutory definition of "source",
B. The Corps
The justifications advanced by the Corps for not preparing an EIS have already been rejected. Defendant HECO, however, contends that 33 U.S.C. § 1371(c)(2) provides the Corps with an exemption from its NEPA responsibilities. HECO's argument is rejected for two reasons.
First, it is well established that an agency cannot support its action or inaction by reference to reasons which it did not rely on at the administrative level. See, e. g., Burlington Truck Lines v. United States, 371 U.S. 156, 168-69, 83 S.Ct. 239, 9 L.Ed.2d 207 (1962). In this case, only HECO, but not the agency, has relied on 33 U.S.C. § 1371(c)(2) in its presentation to this court and therefore this argument must be rejected.
Second, even if the court were to consider HECO's contentions, they would have to be rejected. The statutory provisions on which HECO relies state only that NEPA does not authorize any federal agency to "review any effluent limitation or other requirement established pursuant [to the FWPCA]," 33 U.S.C. § 1371(c)(2)(A), or to "impose" any effluent limitation in connection with the issuance of a federal permit or license. See 33 U.S.C. § 1371(c)(2)
HECO claims that the preparation of an EIS and the possible denial of a Corps permit based on environmental concerns would necessarily constitute "review" or "imposition" of an effluent limitation since the design and location of the discharge structure are allegedly part and parcel of the effluent limitation. Even assuming that the definition of the term effluent limitation is as broad in this and other respects as HECO claims,
The legislative history of 33 U.S.C. § 1371(c) reveals that it was inserted by the Conference Committee with only the sparse explanatory statement that this provision "clarifi[ed] certain relationships" between the FWPCA and NEPA. See S.Rep.No.92-1236, 92d Cong., 2d Session 149 (1972) U.S. Code Cong. & Admin.News 1972, pp. 3668, 3776. Several Congressmen explained in greater detail the purposes of 33 U.S.C. § 1371(c)(2)(A) and (B), and made it clear that "nothing in [those sections] should in any way be construed to discharge any federal licensing or permitting agency, other than EPA, from its full range of NEPA obligations to make a systematic balancing analysis of the activity proposed to be licensed or permitted." 118 Cong.Rec. 33701 (1972) (remarks of Senator Muskie). The statements of Representative Jones, 118 Cong.Rec. 33751 (1972) and Representative Dingell, 118 Cong.Rec. 33759 (1972) are to the same effect.
Since EPA is statutorily exempted from preparing an EIS for the discharge facility at issue, HECO urges that it is "absurd" to require an EIS "simply" because a Corps permit is required. The court is reassured that its interpretation of the statutory language and history is correct by recognizing the consequences which a contrary interpretation has had in this case. The result of the combined action of EPA and the Corps at Kahe has been to permit, if not to require, HECO to construct a concrete wall through the middle of a prime surf site in order to achieve compliance with a statute which lists as one of its prime purposes the achievement of "water quality . . . which provides for recreation in and on the water . . .". 33 U.S.C. § 1251(a)(2). An EIS might have avoided this tragedy.
III. Relief
A. Laches
Defendant HECO urges that the facts of this case mandate that plaintiffs' claims be barred by laches. HECO began applying for federal permits to build the Kahe discharge facility over three years before suit was filed. Various public notices and hearings brought almost no adverse public reaction. Six days after the final permit was issued on January 16, 1976, construction on the discharge facility began. The complaint in this case was filed on April 9, 1976, and plaintiffs' motion for a preliminary injunction was filed on May 22, 1976.
HECO introduced evidence, which went uncontradicted, that by the time suit was filed it had completed 16 per cent of the project at a cost of slightly less than $1.2 million. The work on the project was 25 per cent complete when the motion for a preliminary injunction was heard; by that time, HECO had spent almost $2 million. Under these circumstances, HECO urges that laches should apply.
Two essential elements are required before laches will apply to a claim brought under NEPA. There must be a "lack of diligence by plaintiff and injurious reliance thereon by defendant. . . ." See Lathan v. Volpe, 455 F.2d 1111, 1123 (9th Cir. 1971) and see also Lathan v. Brinegar, 506 F.2d 677, 692 (9th Cir. 1974).
Generally, only delay in the assertion of a legal right which plaintiffs knew about (or should have known about) will constitute the requisite lack of diligence. See City of Davis v. Coleman, 521 F.2d 661, 677 (9th Cir. 1975) and Concerned About Trident v. Schlesinger, 400 F.Supp. 454, 478 (D.D.C.1975). In this case, until the actual construction began, the plaintiffs were unaware of the nature of the serious changes which the discharge facility would create in the Kahe area. The public notices which HECO claims should have alerted plaintiffs did not clearly indicate the offshore consequences of the proposed project; that is, the wall which extends through the surfing area at Kahe. It was only after the commencement of the actual construction revealed the nature of the threat to the area that loosely organized citizens' groups such as the one involved in this case galvanized and sought legal redress. See Steubing v. Brinegar, 511 F.2d 489, 495 (2d Cir. 1975), Jones v. Lynn, 477 F.2d 885, 892 (1st Cir. 1973) and Arkansas Community Org. for Reform Now v. Brinegar, 398 F.Supp. 685, 691 (E.D.Ark.1975), aff'd 531 F.2d 864 (8th Cir. 1976).
HECO claims that plaintiffs were not diligent because they waited approximately seven weeks between the filing of their complaint and the filing of their motion for a preliminary injunction. Even if plaintiffs were not diligent in this respect, the court is not convinced that this lack of diligence after suit has been filed is relevant to HECO's claim that laches bar plaintiffs' claims. Furthermore, HECO cannot claim that it injuriously relied on this delay. Any prejudice suffered by HECO during this period resulted from HECO's decision to continue construction without moving this court for judgment in its favor.
B. Propriety of Injunction
After a hearing on plaintiffs' motion for a preliminary injunction, the court issued the requested injunction in view of the strong likelihood that plaintiffs would prevail on the merits and the irreparable harm to the plaintiffs stemming from the violation of NEPA by the Corps. See Minnesota Public Interest Research Group v. Butz, 498 F.2d 1314, 1323 (8th Cir. 1974) and Scherr v. Volpe, 466 F.2d 1027, 1034 (1st Cir. 1972).
Subsequent to a hearing on the plaintiffs' motion for a permanent injunction, the court continued the preliminary injunction
C. Conclusion
The parties reported back to the court with an agreement whereby HECO would attempt to construct a surf site near the original site in exchange for plaintiffs' dismissal
FootNotes
42 U.S.C. § 4332(2)(C).
Comment
User Comments