Order unanimously affirmed, with costs.
Memorandum:
Plaintiff seeks to recover $30,000 damages for breach of contract in the alleged defective construction of an eight-inch water line by defendant contractor. Defendants, the contractor and its surety, moved for summary judgment alleging compromise and settlement of the dispute and that the action was time-barred. It is alleged in support of the motion that on or about September 22, 1971 the town and the contractor...