AEROSTATIC ENGINEERING CORP. v. SZCZAWINSKI


1 Mass. App. Ct. 141 (1973)

294 N.E.2d 521

AEROSTATIC ENGINEERING CORP. vs. CHESTER SZCZAWINSKI, trustee.

Appeals Court of Massachusetts, Middlesex.

March 2, 1973.


Attorney(s) appearing for the Case

Bruce N. Sachar for the defendant.

John D. O'Reilly, III, for the plaintiff.

Present: ROSE, GOODMAN, & ARMSTRONG, JJ.


ROSE, J.

The plaintiff, pursuant to a written agreement with the defendant, performed a substantial part of a $60,000 contract before terminating it because of the defendant's asserted refusal to make payments as they became due under the contract. The plaintiff seeks in one count to recover $54,000 allegedly due under the contract and in a separate count to recover the same amount on an account annexed for labor and material furnished to the defendant. The plaintiff...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases