Judgment unanimously reversed on the law and facts, with costs, and judgment granted in favor of petitioner in accordance with the following Memorandum: Bid specifications insofar as they require the general contractor's superintendent to correlate all the work on the job, the separate prime contractors to coordinate their work schedules with that of the general contractor, and hold the general contractor responsible for setting the pace for the job and for all work in place...