MALAN CONSTR. CORP. v. ALLIS-CHALMERS MFG. CO.


35 A.D.2d 788 (1970)

Malan Construction Corp., Now Known as Unicon Management Corp., and Buckley & Company, Inc., a Joint Venture Known as Malan-Buckley, Respondents, v. Allis-Chalmers Manufacturing Company, Appellant

Appellate Division of the Supreme Court of the State of New York, First Department.

November 5, 1970


Appellant shall recover of respondents $30 costs and disbursements of this appeal.

During March, 1963, defendant-appellant agreed to sell to plaintiffs-respondents certain equipment for an agreed price. The contract contained a valid arbitration clause limiting the function of the arbitrator to making findings of fact and not conclusions of law. Arbitrable disputes between the parties arose prior to September, 1966. Defendant filed a lien on September 26, 1966. On...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases