Motion for Rehearing or for Transfer to Court En Banc Denied July 12, 1965.
EAGER, Presiding Judge.
This is a suit by a subcontractor and his assignee upon a performance and payment bond furnished to cover labor and materials on a government project. The defense is that the subcontractor did not properly perform his contract and is not entitled to the balance allegedly due. Plaintiff-assignee recovered judgment, in a trial without a jury, for $15,754.23 and...