DURFEE, Judge.
This case involves a claim for equitable adjustment for the alleged "additional value" of building block that was used in construction of buildings on the Air Force Base at Homestead, Florida.
The principal issue before us is whether plaintiffs have suffered damages as a result of defendant's rejection of a building block and the consequent requirement that plaintiffs substitute a different block, where the price paid for the two different blocks was the same.
Plaintiffs entered into a contract, DA 08-123-ENG-1595, with the Corps of Engineers on September 15, 1954. The contract involved construction of 18 airmen's dormitories, five mess halls and three bachelor officers' quarters. The total contract price was $4,867,605.30.
The buildings were to be constructed of concrete building block with exposed surfaces "of a fine texture generally produced in the Florida area which is suitable for painting as distinguished from `coarse textured block' produced for the purpose of receiving stucco or plaster * * *." (Paragraph 5-02(c) Materials).
Plaintiffs placed an order for suitable block with a supplier. Subsequently, on or about January of 1955 the contracting officer rejected the concrete block submitted by plaintiffs, and required the use of a "sand block." Plaintiffs then requested additional compensation in the amount of $312,016.60 to defray alleged additional costs. The matter was processed and Modifications Nos. 45 and 46, dated May 13, 1957, and April 4, 1958, respectively, were issued. These Modifications allowed plaintiffs $125,624.39 to compensate them for the cost of additional labor required in handling and placing the block, and for handling and hauling the rejected block. Plaintiffs' claim of $42,415.98 for the alleged additional value of the sand block over and above the value of the originally specified block was denied by the contracting officer and, ultimately, by the Armed Services Board of Contract Appeals.
Though the price which plaintiffs actually paid for the "sand block" was the same as they would have paid for the original block selected, they contend that the fair market value of the sand block was greater than the purchase price. Essentially then, plaintiffs argue that
Though there is substantial controversy as to the market value of the sand block as of the time of the transaction between plaintiffs and their supplier, for purposes of defendant's motion for partial summary judgment, we are called upon only to decide the narrow question whether "cost" or "fair market value" controls in the award of an equitable adjustment.
Equitable adjustments in this context are simply corrective measures utilized to keep a contractor whole when the Government modifies a contract. Since the purpose underlying such adjustments is to safeguard the contractor against increased costs engendered by the modification, it appears patent that the measure of damages cannot be the value received by the Government, but must be more closely related to and contingent upon the altered position in which the contractor finds himself by reason of the modification. We held this view in the early case of McFerran v. United States, 39 Ct.Cl. 441 (1904). The contract there involved construction of structures at Fort Ethan Allen. The specifications called for the use of cut stone. The quartermaster in charge required that claimant furnish marble. Judge Weldon, speaking for the court in disallowing the claim, stated (39 Ct.Cl. p. 451):
Clearly, in that case the holding of the court was based on cost and not on fair market value. The instant case falls squarely under, and is controlled by, McFerran, supra.
The Armed Services Board of Contract Appeals, in its consideration of plaintiffs' case, assumed plaintiffs' statement of law, but held against them on a finding of fact that the price plaintiffs had paid for the stone was actually its fair market value. But fair market value is not the measure of damages in this case. This is not to say that in all cases, historical cost is to be the gauge. The more proper measure would seem to be a "reasonable cost." The concept of "reasonable cost" is not new. Indeed, it has been defined in the following manner:
Use of the "reasonable cost" measure does not constitute "an objective and universal procedure, involving the determination of the reasonable value (or reasonable cost of any contractor similarly situated) of the work involved;"
But the standard of reasonable cost "must be viewed in the light of a particular contractor's costs * * *"
To say that "reasonable cost" rather than "historical cost" should be the measure does not depart from the test applied in the past, for the two terms are often synonymous. And where there is an alleged disparity between "historical" and "reasonable" costs, the historical costs are presumed reasonable.
Applying the "reasonable cost" test to plaintiffs' hypothetical situation of a contractor purchasing blocks in New York State and paying haulage to Florida,
Though considerable uncertainty seems to exist as to what test has been applied in the past,
No doubt some of the uncertainty in this area is due to the fact that in some cases historical or actual cost, reasonable cost and fair market value are the same, while in others, reasonable cost may be the same as either fair market value or historical or actual cost, and in still others, reasonable cost may be neither fair market value nor historical or actual cost.
As plaintiffs themselves point out at p. 6 of their brief:
To support this statement, plaintiffs cite F. H. McGraw and Co. v. United States, 130 F.Supp. 394, 131 Ct.Cl. 501 (1955), and Oliver-Finnie Co. v. United States, 150 Ct.Cl. 189, 279 F.2d 498 (1960).
Plaintiffs here have not been able to overcome the presumption that their actual costs were reasonable, hence they may not recover. From the record, it is clear that the only evidence plaintiffs introduced tended to prove the fair market value of the blocks some eighteen months after the transaction. We are here not required to say that evidence of fair market value subsequent to a transaction is sufficient to prove fair market value at the time of transaction. We do say, however, that evidence of the fair market value of an item some eighteen months after a transaction involving the item does not rebut the presumption that the cost of the item was reasonable at the time of the transaction.
Defendant's motion for partial summary judgment is granted, and plaintiff's cross motion is denied. That portion of the petition involving plaintiffs' claim for $42,415.98 for "additional value" of building block, as set forth in the First Count of the petition is, accordingly, dismissed.
LARAMORE, Judge (concurring in the result).
I concur for the reason that the only evidence of value at the time was the invoice showing the price plaintiff paid for the blocks. In the absence of any other evidence of value at the time of the purchase, I would adopt the invoice price as the proper measure of value.
Comment
User Comments