SPIEGEL, J.
This is a bill in equity to enjoin the defendants from "discharging and throwing water in an artificial stream on the land" of the plaintiff and for damages. The suit was referred to a master. Each of the parties filed objections to the master's report. The court below entered an interlocutory decree in which the exceptions of all the parties were overruled and various motions filed by the "several parties" were denied and recommittal to the master for further findings as follows was ordered:
"1. That further facts be reported after taking additional testimony, if required, for the purpose of applying a correct measure of damages in accordance with the principle of establishing damages suggested in Belkus v. City of Brockton, 282 Mass. 285, more particularly, to report facts which would indicate to the Court whether — if, the injury
"2. That the master report facts which would indicate to the Court — if the act is continuous, but subject to termination by the later act of the ... [defendants], the lessened rental value while the injury continued to the date of the bill."
None of the parties appealed from this decree.
After the master's report on recommittal each of the parties filed objections to that report which, under Rule 90 of the Superior Court (1954), are treated as exceptions. An interlocutory decree was entered overruling the exceptions of the plaintiff and the defendant Pinewood Builders, Inc., sustaining the exceptions of the town of Framingham, and ordering the master's report and report on recommittal "confirmed as so modified." Pinewood Builders, Inc. (hereinafter referred to as Pinewood), appealed from this decree. The court entered a final decree ordering Pinewood to pay to the plaintiff $21,750 plus interest and in "all other respects ... dismissed" the bill, from which the plaintiff and Pinewood appealed.
A summary of the material facts found by the master follows. In 1931, the plaintiff purchased a parcel of land consisting of about forty-three acres in the towns of Framingham and Sudbury. In 1953, the plaintiff sold a portion of this land to the Lexington Sand & Gravel Co. and as a part of the transaction granted that company an easement for five years to "... dump waste water and waste material upon, and ... erect, maintain, and operate ... equipment" on a part of the plaintiff's remaining land. By deeds dated January 10, 1959, and May 15, 1959, the Lexington Sand & Gravel Co. "transferred its title in the land originally belonging to" the plaintiff to the defendant Pinewood. The parcel of land to which the plaintiff retained title comprised approximately fourteen and a half acres. In 1931, all of the land was in a "wild and undeveloped state" and "had a tendency to become damp and wet as a result of the flood of natural water onto it from surrounding
In 1959 and 1960, immediately after its purchase of the land from the gravel company, Pinewood embarked upon a project to develop its land, together with some land adjacent thereto, for several hundred housing units "under the name of Woodfield I, II, and III." Pinewood, with the approval and permission of the planning board of Framingham and the permission of the town engineer and members of the engineering department, then graded the land so that it gradually sloped in a descending plane toward the plaintiff's land. As a part of this authorized plan a surface water drainage system was installed which caused all of the surface water from the area to be collected into the drains and then to be discharged on the land of one Raymond from which it spilled over onto the plaintiff's land. Upon the complaint of the plaintiff, Pinewood conferred with a representative of Framingham and "it was determined that it would be better for all parties ... to defend one law suit instead of two." As a result thereof a new drain was constructed which discharged the surface water at the boundary of the plaintiff's land alone, avoiding the Raymond property.
There never was any natural watercourse "existent" from Pinewood's land running over the plaintiff's land. Pinewood's construction "created a substantial additional burden" on the plaintiff's land making the plaintiff's drainage system inadequate to drain off the water and this resulted in water backing up and flooding the plaintiff's land. Pinewood's actions were "intentional," "deliberate," and "tortious." It "knew the full effect and result of its construction
In his supplemental report the master found that twelve and a half acres of the plaintiff's land were either flooded or affected by the flooding, and the value of that land to be $21,750, which figure was adopted by the court in its final decree.
1. The plaintiff contends that he is entitled to injunctive relief against both defendants and not merely damages from Pinewood. Subject to the possibility of certain additional findings of fact to which we shall refer later in this opinion we hold that injunctive relief should be decreed against Pinewood. Without the pretext of an easement or other legal right, Pinewood has artificially collected, channeled, and discharged its surface waters onto the plaintiff's land. Such action constitutes a continuing trespass. Manning v. Woodlawn Cemetery Corp. 245 Mass. 250, 251. Fortier v. H.P. Hood & Sons, Inc. 307 Mass. 292, 296. Miller v. Darby, 336 Mass. 243, 246. An intentional and continuing trespass to real estate may be enjoined. Ottavia v. Savarese, 338 Mass. 330, 336. Damages are usually inadequate because the plaintiff is not to be compelled to part with his property for a sum of money. "The principal reason for this is that which lies at the foundation of the jurisdiction for decreeing specific performance of contracts for the sale of real estate. A particular piece of real estate cannot be replaced by any sum of money, however large,
Injunctive relief has been denied in exceptional circumstances such as those found in Gray v. Howell, 292 Mass. 400, and Triulzi v. Costa, 296 Mass. 24. See Caputo v. Board of Appeals of Somerville, 330 Mass. 107, 112; Tehan v. Security Natl. Bank, 340 Mass. 176, 182; Nassif v. Boston & Maine R.R. 340 Mass. 557, 566.
The only finding apparent to us in the present state of the record for denying injunctive relief is to the effect that a permanent injunction "may cause hardship to several hundred bona fide and innocent purchasers of property in Woodfield I, II and III." This finding, while inconclusive, raises a question which should be answered before a decree for injunctive relief becomes effective. It may be that the only alternative to the use of the plaintiff's land in the building of a drain is the uprooting or destruction of some property of innocent purchasers of lots from Pinewood. It is conceivable that there is no other physically possible means of draining the property of bona fide purchasers or that the cost of an alternative is outrageously disproportionate to the benefit to be derived by the plaintiff.
Further hearings before the master or in the Superior Court, as the court may decide, must be held to ascertain whether there are such offsetting equities in this case.
2. If an injunction is granted a different rule for damages is required. Neither the fair market value of the plaintiff's "affected" land nor the cost of constructing a remedial drain under his property, the only measures for damages found below, will properly compensate the plaintiff.
3. The remaining issue to be determined is whether the plaintiff is entitled to injunctive relief against Framingham. Surface waters from land belonging to Framingham are being channeled through the Pinewood surface water drainage system and discharged upon the plaintiff's land. This, too, is a continuing trespass and the plaintiff prays that Framingham be restrained from "discharging and throwing water" on his land. The master found that such water "can be adequately diverted from the present system to another system in such fashion" that the plaintiff's land "will be free of any future flow from ... Framingham's land." The plaintiff is entitled to have the town enjoined from the continuation of the trespass. Turner v. Oxford, 338 Mass. 286, 289. Lenari v. Kingston, 342 Mass. 705, 709. No contention is made that Framingham is liable in damages.
4. Admittedly, the factual situation before us is unusual. Pinewood may argue that its position is the result of the action of the planning board of Framingham and, therefore, Pinewood should not be held responsible. While this may be Pinewood's reason for the continuing trespass, and while it may have no ill intent, nevertheless, this does not alleviate the damage to the plaintiff caused by the drainage system.
5. Litigation on this issue cannot be permitted to continue ad infinitum. Permanent injunctive relief is required
6. Conceivably, additional complications may arise which will present issues for the judge's determination. To avoid the necessity of additional litigation over substantially the same issues, we think it advisable that the Superior Court retain jurisdiction of the case and the parties. "Such retention of jurisdiction is not unusual." Nassif v. Boston & Maine R.R. 340 Mass. 557, 566.
7. We perceive no point in enumerating the exceptions of Pinewood to the master's supplemental report. Those which merited discussion have been dealt with in this opinion.
8. The interlocutory decrees are reversed; the final decree is reversed; and the case is remanded to the Superior Court for further proceedings consistent with this opinion.
So ordered.