LUMBARD, Chief Judge.
The Glidden Company appeals from a judgment dismissing its libel in admiralty to recover damages for the alleged breach of four charter parties between it and Hellenic Lines, Limited. The suit, brought about by Hellenic's admitted failure to perform the contracts because of the closing of the Suez Canal on November 2, 1956 in the Israeli-Egyptian war, presents an interesting problem in the law of frustration of
The libel alleged that Glidden and Hellenic had entered into four charter parties, the first on September 7, 1956 and the other three about November 1, 1956, in which Hellenic undertook to carry four cargoes of ilmenite, an order containing iron oxide and titanium dioxide, used by Glidden in the manufacture of compounds from which paint and other products are made, from Koilthottam, India, to a United States Atlantic port north of Cape Hatteras. The first charter party called for the carriage of 9,000 to 10,000 long tons at a rate of $16 per ton with the vessel, the Hellenic Sailor, to be tendered at Koilthottam not later than November 30, 1956. Under the other three charter parties a total of approximately 25,000 tons of ilmenite was to be carried at a price of $18.50 per ton with the ships to be tendered in December 1956 and January and February 1957. As a result of Hellenic's failure to perform any of the contracts Glidden was required to hire other vessels with a lesser capacity and to curtail its manufacturing operations, for which it sought damages of $540,000.
In its answer Hellenic asserted that as to all four agreements the parties' intention was that the ships would travel from Koilthottam to the United States via the Suez Canal, that the closing of the Canal from November 2, 1956 to about April 10, 1957 prevented use of this route and that the contracts were thereby frustrated and performance excused. Alternatively Hellenic maintained that the closing of the Canal by Egypt exonerated it under a force majeure clause of the charter parties, excepting "restraint of princes and rulers" and "other dangers and accidents of the seas" or under § 4 of the Carriage of Goods by Sea Act, 46 U.S.C.A. § 1304, incorporated by reference in the charter parties, absolving the carrier of responsibility for loss resulting from an "act of war" or "any other cause arising without the actual fault * * * of the carrier." Two additional defenses, applicable only to the three contracts of November 1, 1956, will be referred to hereafter.
After a trial, Judge Knox, relying upon the recent English decision in Carapanayoti & Co. v. E. T. Green, Ltd., [1958], 2 Lloyd's List L.R. 169,
The doctrine of frustration of contracts provides, generally, that where the existence of a specific thing is, either by the terms of the contract or in the contemplation of the parties, necessary for performance of a promise in the contract, the duty to perform the promise is discharged if the thing is no longer in existence at the time for performance. Restatement of Contracts § 460. Whether the doctrine is applicable to excuse performance by Hellenic turns upon the interpretation of a clause appearing in each of the four charter parties. The clause states that each charter shall be "for a voyage from Koilthottam, India, via Suez Canal or Cape of Good Hope, or Panama Canal, at Owner's option declarable not later than on signing of Bills of Lading, to one safe U. S. Atlantic Port North of Cape Hatteras, port
Hellenic argues that it was the intention and expectation of the parties that the voyages would be via Suez, which it asserts is the only economically feasible route,
We find the words of the charter parties taken by themselves to be susceptible to either interpretation. No doubt the parties anticipated that the vessels would be likely to travel the customary route via Suez and inserted the typewritten provision for giving notice with this expectation in mind. However, we find difficulty in implying from this insertion an intention to abrogate other specific references to alternative routes appearing in the same sentence of the charter parties, as it seems to us improbable that experienced businessmen, intent upon changing the terms of a printed contract, would act in so ambiguous and indirect a fashion. Moreover, if the contracts are construed to impose upon Hellenic a duty to perform via an alternative route in the event that Suez were closed, it is logical to imply an alternative obligation upon Glidden to give reasonable notice to the shipowner of the port selected for unloading.
Because the words of the contracts are thus ambiguous, we turn to an examination of the surrounding circumstances for aid in their interpretation. Hellenic says that we may not do this, that we must find the meaning of the charter parties within the four corners of the instruments, and that it was error for the trial court to admit evidence of the negotiations leading up to the signing of the September 7 charter. We do not agree. Previous negotiations, as well as other circumstances surrounding the contract negotiations, are admissible
When we look to the negotiations leading to the signing of the charter parties, we find clear support for Glidden's interpretation. At the time of these negotiations, the Egyptian government had already nationalized the Suez Canal and the possibility of war in the Sinai Peninsula and the closing of the Canal were discussed in the public press and were recognized by the parties. In prior contracts with National Lead Company for the carriage of cargoes of ilmenite between similar points, Hellenic had sought and obtained a clause specifically excusing performance by it in the event that eastward transit of the Canal was impossible.
What we have said thus far applies equally in rejecting Hellenic's arguments based upon the force majeure clause of the charters and § 4 of the Carriage of Goods by Sea Act. These provisions could only come into operation to exculpate Hellenic in the event it was prevented from performing by one of the causes therein described. Since we have already decided that Hellenic was under a duty to perform by an alternative route these provisions have no applicability.
Hellenic raises two further arguments which relate only to the last
The first of these questions turns upon whether the parties intended to be bound at the time they orally agreed upon the terms of the contract or whether it was the intention of both of them, or the intent of either manifested to the other, not to be bound until a formal written document was executed. Banking & Trading Corp. v. Floete, 2 Cir., 1958, 257 F.2d 765; Restatement of Contracts §§ 25, 26. Here, the fact that the charters involved large sums of money, were to be performed over a considerable period of time, and contained numerous details all suggest that written agreements were intended. On the other hand, the fact that the contracts were similar to one previously agreed to by the parties and that the negotiations immediately preceeding November 1 were confined to bargaining about the freight rate suggests that the parties, once agreement was reached upon the price, intended to be bound. Moreover, a letter from Hellenic to Glidden's chartering broker, written on November 8, lends strong additional support to the trial court's conclusion. In this letter by Hellenic by its assertion that the three charter parties were frustrated by the closing of the Canal impliedly acknowledged that prior to this event it regarded the contracts as binding.
Similarly, the trial court's determination that Pendias was authorized to act for Hellenic is justified by the record. The same letter from Hellenic referred to above supports the view that Hellenic regarded its agent's conduct as binding upon it. There was also abundant other evidence to support the court's finding that Pendias had either authority or apparent authority to enter into the charters. He had signed the earlier charter for Hellenic by his own signature, as well as virtually all of the extensive correspondence among Hellenic, Glidden and Glidden's broker; all the negotiations with Glidden had been carried on by him alone.
Because the trial court decided that the charter parties were frustrated, it received no evidence and made no findings of the plaintiff's damages. We therefore remand the case for the determination of this question.
Reversed and remanded.
FootNotes
"Effective closure of the Suez Canal, preventing eastward transit of the Owners' vessels to the Persian Gulf-Indian Ocean area, shall be deemed to be frustration of the Owners' obligation to tender such vessels to the Charterers for loading and of the Charterers' obligation to ship under this Agreement, as long as the Suez Canal remains closed."
Comment
User Comments