The complaint sets forth two causes of action for breach of contract. In the first cause of action the contract was for the erection of a one-car garage for the sum of $1,600. As to this plaintiff sues for $552, basing the claim on a clause of the contract which provides for liquidated damages of 30% of the total contract price and an additional 15% for attorney's fees. In the second cause...