Claimant was awarded the heating contract, which included ventilating ducts, in connection with the construction of a nine-story building at Hudson River State Hospital. Claimant contends that it was required to install and did install, under protest, a greater quantity of stainless steel ducts than called for by the contract and specifications. The basis of the claim is the difference in cost between stainless steel ducts and galvanized iron ducts, claimant contending that...