WILKINS, J.
These two cases, which were tried together, present the same principal question: Was John Bowen Co., Inc., the "lowest responsible and eligible" general bidder on a contract for the construction of a chronic diseases hospital in Boston, a project subject to G.L. (Ter. Ed.) c. 149, §§ 44A-44D, inserted by St. 1939, c. 480, as amended?
Not less than twenty-four (to wit, twenty-eight) taxable inhabitants of the Commonwealth, not more than six of whom are from any one county, bring this petition under G.L. (Ter. Ed.) c. 29, § 63, inserted by St. 1937, c. 157. The respondents are the commissioner of public health, the commission, the Treasurer and Receiver General, and Bowen.
In August, 1951, the department publicly invited sealed proposals for the construction of the hospital in accordance with certain plans and specifications. In the proposal form the department designated twenty-seven subcontractors to be included by each general contractor in Item 2 of his bid. Pursuant to, and in the language of, G.L. (Ter. Ed.) c. 149, §§ 44C (A), (B), inserted by St. 1939, c. 480, the notice to contractors provided: "Bids from general contractors shall be for the complete project as specified and shall include the names of all principal and such minor sub-contractors as are designated in the proposal form, and the general contractor shall be selected on the basis of such bid. Each bid shall be divided into two items: Item 1, covering all the work of the general contractor, being all work not covered in Item 2. Item 2, covering the work of such sub-contractors, and the estimates therefor, as are listed in the proposal form for general contractors, attached thereto.... No sub-bid shall be considered in the final selection of sub-bidders... except those filed with the awarding authority." The notice to contractors also contained the following: "No amount shall be included by a bidder in either Item 1 or Item 2 of the proposal form for the work to be performed under an item or items listed in Item 2 on which no recorded sub-bids have been received, and the bids of general contractors will be compared only on such basis."
Other provisions of § 44C (B), as amended, are: "All principal and such minor sub-contractors as are designated in the proposal form shall deliver or mail to the awarding authority record copies of all bids sent by them to the general contractor.... No recorded sub-bids shall be opened
As later extended, the filing time for subbids closed on October 2, 1951, and for bids on October 5, 1951. Many subbids were filed for twenty-six
It thus appeared that on Item 1, which was the work to be done by the general contractor, Slotnik's bid was lower by $21,784. But on Item 2, which was the work to be done by subcontractors, Bowen's bid was lower by $21,942.75, notwithstanding that Slotnik and Bowen had named the same twenty-six subbidders and had received the same subbids from them. On October 22, 1951, Bowen, whose total bid seemed to be lower by $158.75, was recommended by the department as the "lowest responsible and eligible bidder," and on October 24 the commission voted to approve the award of the contract to Bowen.
In the meantime on October 11, 1951, the recorded subbids, which had been filed with the department, were opened and read. It then could be seen that the recorded subbids of twenty-one subcontractors named by both Slotnik and Bowen were identical with the estimates submitted by
The notice to contractors signed by the commissioner and the special form for general bidders (prepared by the department and signed by Slotnik and Bowen) provided that a subbidder may be required by the general contractor or the awarding authority to furnish a performance bond. The same special form also contained the provision: "The undersigned agrees that the list of subbidders represent bona fide bids based on the plans and specifications, made in good faith to the bidder, and are hereby submitted and that, if the undersigned is awarded the contract, they will be used for the work indicated, at the amounts stated, if satisfactory to the awarding authority as provided in the general conditions."
The foregoing facts are found by us from the statements of counsel at the hearing in the court below and from documents in evidence. The judge filed a paper containing findings, rulings, and an order for decree. The petitioners appealed from a final decree dismissing the petition. The evidence is reported.
We here summarize certain evidence relating to the difference of $20,000 in the use made by Slotnik and that made by Bowen of the Johnson-Foster painting subbid. The original specifications called for the subcontractor to
The trial judge ruled that the requirements of c. 149, §§ 44A-44D, as amended, were complied with by the commission and by Bowen. He made so called findings that there were no "irregularities" by Bowen in its treatment of the subcontracts for marble, tile, and painting; that with respect to the marble and tile bids Bowen "had the right to disregard the suggestion that an additional three quarters of one per cent be added to the bids if performance bonds were required"; and that with respect to the bid for painting "the estimated cost of $20,000 for fabron wall covering was not omitted by the Bowen Co., but was carried in Item 1 where it properly belonged." Referring to the addendum of September 14, 1951, the judge also stated, "when these changes in the original came to the attention of the painting subcontractor, he gave notice to the Bowen
We are of opinion that the rulings of law were in error, and if there was anything which might properly be called a finding it was plainly wrong. One purpose of the statute is to make certain that general contractors shall be on an equal basis as to the bids of subcontractors. The recorded subbids, as filed, must be strictly adhered to, and cannot be varied. A subbid once filed by a subcontractor must have an identical meaning for all general contractors. After the time for filing has expired, a subbid is not subject to change, and is, of course, beyond modification by private, confidential, or secret communication between the subcontractor and the general contractor. Similarly, after the time for filing has expired, a general contractor is bound by his bid as filed, and no form of testimony, written or oral, can be received to prove that the bid had some meaning not ascertainable on its face.
The application of these principles to the case at bar is plain. As for the painting subbid, neither the department nor the commission could give weight to the statement made on behalf of Bowen that in its bid the cost of fabric wall covering was included in Item 1. If the specifications required that to be done, a bidder would be held to the specifications; and if not, no statement of the kind could avail him. Evidence that Bowen included such cost in Item 1 should not have been admitted in the Superior Court, and this exception of the petitioners must be sustained. We need not consider a subsidiary controversy as to whether "contractor" meant "general contractor" or "sub-contractor" in the specifications as amended. That the specifications were lacking in desirable clarity in this respect is evident from the conflicting arguments as to their interpretation.
No great imagination is needed to comprehend the evils that might befall if the statute could be circumvented in the respects noted in this case. Whether the "end result in dollars" for painting and for fabric wall covering is the same under both bids cannot afford any latitude to the awarding authority to disregard the statute. Bowditch v. Superintendent of Streets of Boston, 168 Mass. 239, 244. Warren v. Street Commissioners of Boston, 181 Mass. 6, 11. Even if it were supposed that some violation of the law resulted in a benefit to the Commonwealth, that circumstance would be irrelevant. Conners v. Lowell, 246 Mass. 279, 282. Nor is the reservation of a right "to reject any and all proposals" in the notice to contractors the source of any option to disobey the statutory mandate.
This is not a question of the courts awarding the contract.
There remains for consideration a matter of procedure. The respondents have filed with us a motion to dismiss the appeal on the ground that the petitioners gave no order in writing for the preparation of the necessary papers and copies of papers for transmission to the full court within ten days after the case became ripe for final preparation and printing of the record. G.L. (Ter. Ed.) c. 231, § 133, as amended by St. 1933, c. 300, § 2; § 135, as amended by St. 1941, c. 187, § 1. The final decree was entered on November 16, 1951, and on the same day the petitioners filed a claim of exceptions. On November 23, the petitioners filed an appeal, and on November 28 a bill of exceptions. On December 3 (the last day for ordering the printing according to the contention of the respondents) the trial judge approved a stipulation providing for the printing of a consolidated record for this case and the second case discussed below, which is a petition for a writ of certiorari by Slotnik against the commission. The stipulation stated that "whereas said proceedings were heard together in the Superior Court, for the purpose of the presentation of each said proceeding to the Supreme Judicial Court of any and all appeals and exceptions therein, the records of said proceedings be prepared and printed as a consolidated record in so far as said record may be applicable to each proceeding." On the same date the judge approved another stipulation in both cases providing that certain exhibits and documents
In the second case, the petition for a writ of certiorari, a judgment for the respondents was entered on November 21. The petitioner appealed on November 28.
The respondents' contention is that the case became ripe for final preparation and printing of the record when the appeal was filed on November 23, and that the order for printing the record, which was given on December 4, was not within the ten day period prescribed by G.L. (Ter. Ed.) c. 231, § 135, as amended. They cite such cases as Cherry v. Auger, 300 Mass. 367, and Bass River Savings Bank v. Nickerson, 302 Mass. 235. But these authorities are not in point. Within the ten day period, namely, on December 3, before the time for ordering the printing expired, an order that there should be a consolidated record had been made by the judge. Thereafter there was to be but one record for the two cases. The order obviously did not restrict the time for ordering the printing in the second case. It had the necessary effect of extending the time for doing this act required by § 135, as amended (see Hill v. Trustees of Glenwood Cemetery, 323 Mass. 388, 392), when the extension was secured within the ten day period. Buchannan v. Meisner, 279 Mass. 457, 460-462. Royal Tool & Gauge Corp. v. Clerk of the Courts for the County of Hampden, 326 Mass. 390, 392. Accordingly, the time for ordering the printing of the consolidated record then ran from November 28, the date of the appeal in the second case. There is nothing in Hovhanesian v. New York Life Ins. Co. 310 Mass. 626, 632, which touches this situation. The motion to dismiss is denied.
So ordered.
The requirement that the contract be "approved" necessarily involved the making of findings by the commission and then applying the law to the facts found. For example, they had to determine, as the department already had done, that the project was subject to the statute, a matter not in dispute, and that the contract met the standards established by the Legislature as conditions precedent to favorable action by the awarding authority. G.L. (Ter. Ed.) c. 149, §§ 44A-44D, inserted by St. 1939, c. 480, as amended. Whether Slotnik was a "responsible and eligible" bidder is not presently in issue, as the intention to make such a contention was disclaimed by statements of counsel at the hearing of this case in the court below. The prescribed approval inevitably included making a decision that Bowen was the "lowest responsible and eligible" bidder within the meaning of § 44A. On the record of their acts as disclosed by the return, the commission could not rightly reach this result. The bids and subbids, as they appear in the return, when viewed as the Legislature must have intended, show that Bowen was not the lowest bidder because Slotnik was. There was error of law in the commission's vote of approval of the contract. They proceeded upon an erroneous construction of the statute. Cambridge v. Railroad Commissioners, 153 Mass. 161, 170. Cases like Archambault v. Mayor of Lowell, 278 Mass. 327, where no error of law was shown, are distinguishable.
Judgment is to be entered quashing the decision of the Massachusetts public building commission approving the award by the department of public health to John Bowen Co., Inc., of the contract for "Project No. P-H8 Chronic Diseases Hospital" in Boston.
So ordered.
FootNotes
THE SECOND CASE.
This petition for a writ of certiorari by Slotnik against the commission was heard upon the petition and return. Morrissey v. State Ballot Law Commission, 312 Mass. 121, 124. Sesnovich v. Board of Appeal of Boston, 313 Mass. 393, 399. The case is here upon an appeal from a final judgment dismissing the petition. G.L. (Ter. Ed.) c. 213, § 1D, inserted by St. 1943, c. 374, § 4.
Upon the merits, our decision in the first case is controlling. Although there is no report of the evidence, the return contains substantially the same facts, including written documents and the records of the proceedings of the commission, which in relation to the award to Bowen gave the petitioner a hearing. We must, however, decide whether the petition lies.
It is the function of a writ of certiorari upon a proper and adequate return to correct substantive errors of law by a judicial or quasi judicial tribunal which are not otherwise reviewable by a court. Jordan Marsh Co. v. Labor Relations Commission, 312 Mass. 597, 599. Howe v. Attorney General, 325 Mass. 268, 270. Attorney General v. Board of Public Welfare of Wilmington, ante, 468. G.L. (Ter. Ed.) c. 249, § 4, as amended by St. 1943, c. 374, § 1; c. 213, § 1A, inserted by St. 1939, c. 257, § 1, as amended by St. 1941, c. 180. In approving the contract for the hospital project we think that the commission was acting in a quasi judicial capacity. The statute from which their authority is derived provides that "no construction of any such project shall be undertaken until plans, specifications and contracts therefor shall have been approved by the commission...." G.L. (Ter. Ed.) c. 92A, § 2, inserted by St. 1947, c. 466, § 3. "The word `approval' when it appears in our statutes generally means an affirmative sanction by one person or by a
Comment
User Comments