Ambiguities in the prime contract, which was incorporated into the subcontract, present issues of fact whether plaintiff subcontractor's installation of additional asbestos decontamination units constituted "extra work," thereby triggering contractual notice provisions as a prerequisite to payment for such work (see Discovision Assoc. v Fuji Photo Film Co., Ltd.,