E. P. REYNOLDS, INC. v. NAGER ELEC. CO.


17 N.Y.2d 51 (1966)

E. P. Reynolds, Inc., Plaintiff-Respondent, v. Nager Electric Company, Inc., Defendant-Appellant and Third-Party Plaintiff-Appellant. Massachusetts Bonding & Insurance Company, Third-Party Defendant-Respondent. (And Another Third-Party Action.)

Court of Appeals of the State of New York.

Decided February 17, 1966.


Attorney(s) appearing for the Case

Jerrold Morgulas and Alfred Foreman for appellant.

Alfred J. Klein for respondent.

Chief Judge DESMOND and Judges FULD, VAN VOORHIS, BURKE, SCILEPPI and BERGAN concur.


KEATING, J.

This case reaches us in an unusual posture.

The respondent has recovered a judgment for damages arising out of false representations which induced it into a construction contract with appellant. The appellant's counterclaim for completion cost of the construction in excess of the contract price and the third-party claim against the surety on respondent's performance bond have been disallowed...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases